Asked of 2

  • Question and Answer Session: Transport for London (Supplementary) [19]

    • Question by: Joanne McCartney
    • Meeting date: 06 July 2023
    Joanne McCartney AM: Thank you. My question is for the Commissioner, and I am going to raise the issue of the Piccadilly line signalling upgrade. It is good to hear that you have better relations with Government than previously. We do know that the new trains will increase capacity on the line by 23 percent, but if it were to be given the go-ahead, the signalling would increase capacity by 64 percent. Can I ask you about the state of those negotiations and are you hopeful that we will get that capital funding?
  • Vision for Old Oak Common (Supplementary) [2]

    • Question by: Joanne McCartney
    • Meeting date: 07 September 2017
    Joanne McCartney AM: Thank you. I want to ask about the National Audit Office (NAO) report last year. It was reported in that report that the DfT had asked HS2 to assess the impact of extending the timetable for phase one up to 12 months. I am just wondering what impact that would have on your development schedule?