  • Lead off question - Delays to Crossrail (Supplementary) [1]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you. Mr Mayor, just ten weeks ago, in answer to a Mayoral question (MQ), you stated, “The Elizabeth line remains on course to open as planned in December 2018”. The Commissioner, in the TfL Board report of 25 July [2018] stated, “Crossrail remains on course to open as planned in December”. Sir Terry, on 6 June, when the Transport Committee visited Tottenham Court Road with you, you gave me an absolute assurance that the opening of Crossrail would be in December. You even confirmed the date, Sunday, 9 December when the Queen would be opening...
  • Lead off question - Delays to Crossrail (Supplementary) [6]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Thank you. To come back to Crossrail, on this side [of the table] we definitely recognise the scale of this project but once completed it will be a big success for London. I am definitely looking forward to when it opens. You may be aware of Rob Holden’s [CBE, Chairman, High Speed 1] letter last week in The Times where he stated, “The problems with Crossrail arose from the decision taken in 2011 to delay the procurement of new rolling stock, a decision that has affected the commissioning of those new trains ... signalling was always going...
  • Lead off question - Delays to Crossrail (Supplementary) [9]

    • Question by: Caroline Russell
    • Meeting date: 06 September 2018
    Caroline Russell AM: Thank you, Chairman. I want to ask about the experience of the passengers who are waiting to use this line but before I get on to those questions I want to pick up on something that Sir Terry said at the very beginning. You said, “We mitigated one risk and others materialised”. I wonder if you could expand on that a bit more, whether that is what has caused this decision about the delay.
  • Lead off question - Delays to Crossrail (Supplementary) [14]

    • Question by: Keith Prince
    • Meeting date: 06 September 2018
    Keith Prince AM: Thank you, Chairman. Good morning, Sir Terry. I am trying to get some dates straight in my head. You mentioned a Board meeting in July [2018] where it was raised that there could be problems. Could you tell me the date of that meeting in July, please?
  • Question and Answer Session: Olympic Park Legacy Company

    • Reference: 2011/0075-1
    • Question by: Dee Doocey
    • Meeting date: 16 March 2011
    Dee Doocey (Chair): Can I formally welcome Baroness Ford and Andrew Altman to the meeting. Baroness Ford is the Chair of the Olympic Park Legacy Company (OPLC) and Andrew Altman is the Chief Executive. Thank you very much for coming. If I could explain how the session is going to work; I understand that Margaret and Andrew are going to give a five minute opening statement. I will then ask a Member from each Group to put a question in the following order: the Labour Group, followed by the Liberal Democrat Group, followed by the Conservative Group, followed by the...
  • Question and Answer Session: Olympic Park Legacy Company (Supplementary) [1]

    • Question by: Andrew Boff
    • Meeting date: 16 March 2011
    Could you tell me what role the OPLC will have in consulting the populated parts of the proposed MDC?
  • Question and Answer Session: Olympic Park Legacy Company (Supplementary) [2]

    • Question by: Richard Barnbrook
    • Meeting date: 16 March 2011
    Thank you, Chair. I would like to take a step back as we look towards legacy. We are all aware in this Chamber that the host boroughs of east London are some of the poorest locations in the capital. 70,000 unemployed adults are in the seven east London boroughs that neighbour the Olympic site. I am looking at the foundations of a legacy. How is it possible to truly call this a legacy when, at this moment in time, of the 5,381 employed people on the site, only 20% are from the five hosting boroughs and 48% are non-British? This...
  • Question and Answer Session: Olympic Park Legacy Company (Supplementary) [3]

    • Question by: Jennette Arnold OBE
    • Meeting date: 16 March 2011
    Thank you, Chair. I have got a number of questions. Firstly, to go back to what John was talking about, on the people legacy. The Olympic Park set itself benchmarks, as you know, Margaret. I know that you have been aware of the programmes it implemented. The sadness is that those teams may now well disperse. I welcome what you are doing with schools. Would you agree with me that you need also to work with local colleges, in the way that the ODA did, and what you need to do is, in a sense, take the baton and do...
  • Question and Answer Session: Olympic Park Legacy Company (Supplementary) [4]

    • Question by: Mike Tuffrey
    • Meeting date: 16 March 2011
    Can I touch on the sustainability assurance aspects. The Commission for a Sustainable 2012 does not just do the construction and the staging of the Games, it includes legacy, albeit that process is going to come to an end in about 2013. The first question, for the record, is do you welcome that scrutiny and will you cooperate fully with the Commission for a Sustainable 2012 for the legacy aspects?
  • Question and Answer Session: Olympic Park Legacy Company (Supplementary) [5]

    • Question by: Gareth Bacon MP
    • Meeting date: 16 March 2011
    I am interested in the cost of running the sports venues once they are into legacy mode. I understand that the OPLC will be responsible for the Stadium, the Aquatics Centre, the mixed sports venue and the tower. Do you expect the sports venues will require public subsidy once they are in legacy mode to keep them afloat, or will they stand on their own two feet?