  • Lead off question - Delays to Crossrail (Supplementary) [1]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you. Mr Mayor, just ten weeks ago, in answer to a Mayoral question (MQ), you stated, “The Elizabeth line remains on course to open as planned in December 2018”. The Commissioner, in the TfL Board report of 25 July [2018] stated, “Crossrail remains on course to open as planned in December”. Sir Terry, on 6 June, when the Transport Committee visited Tottenham Court Road with you, you gave me an absolute assurance that the opening of Crossrail would be in December. You even confirmed the date, Sunday, 9 December when the Queen would be opening...
  • Lead off question - Delays to Crossrail (Supplementary) [6]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Thank you. To come back to Crossrail, on this side [of the table] we definitely recognise the scale of this project but once completed it will be a big success for London. I am definitely looking forward to when it opens. You may be aware of Rob Holden’s [CBE, Chairman, High Speed 1] letter last week in The Times where he stated, “The problems with Crossrail arose from the decision taken in 2011 to delay the procurement of new rolling stock, a decision that has affected the commissioning of those new trains ... signalling was always going...
  • Lead off question - Delays to Crossrail (Supplementary) [9]

    • Question by: Caroline Russell
    • Meeting date: 06 September 2018
    Caroline Russell AM: Thank you, Chairman. I want to ask about the experience of the passengers who are waiting to use this line but before I get on to those questions I want to pick up on something that Sir Terry said at the very beginning. You said, “We mitigated one risk and others materialised”. I wonder if you could expand on that a bit more, whether that is what has caused this decision about the delay.
  • Lead off question - Delays to Crossrail (Supplementary) [14]

    • Question by: Keith Prince
    • Meeting date: 06 September 2018
    Keith Prince AM: Thank you, Chairman. Good morning, Sir Terry. I am trying to get some dates straight in my head. You mentioned a Board meeting in July [2018] where it was raised that there could be problems. Could you tell me the date of that meeting in July, please?
  • West London Tram

    • Reference: 2003/0220
    • Question by: Richard Barnes
    • Meeting date: 11 June 2003
    Will he make publicly available the questions asked by ORC International for the TfL opinion poll on the West London Tram released on the 20 March 2003? .
  • West London Tram

    • Reference: 2003/0221
    • Question by: Richard Barnes
    • Meeting date: 11 June 2003
    What is the current estimate for the total cost of the West London Tram? .
  • West London Tram

    • Reference: 2003/0222
    • Question by: Richard Barnes
    • Meeting date: 11 June 2003
    What negotiations have occurred between TfL and private sector companies over PFI financing for the West London Tram? .
  • West London Tram

    • Reference: 2003/0223
    • Question by: Richard Barnes
    • Meeting date: 11 June 2003
    Why has the decision on proceeding with the West London Tram been delayed until January 2004? .
  • Congestion Charge around Heathrow Airport

    • Reference: 2003/0224
    • Question by: Richard Barnes
    • Meeting date: 11 June 2003
    What negotiations have occurred between TfL and British Airports Authority over the introduction of a congestion charge around Heathrow Airport? .
  • Bus Lanes

    • Reference: 2003/0225
    • Question by: Richard Barnes
    • Meeting date: 11 June 2003
    What volume of objections from local residents would be required for TfL to conduct wider consultation on the impact on bus lanes? Who decides if such objections are valid or not? .