  • Lead off question - Delays to Crossrail (Supplementary) [3]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you for that. Will the decision to delay the opening until autumn next year [2019] ‑ it would be great to find out which month in autumn ‑ mean further delay in the opening of the other sections and the final full opening of the line in December 2019?
  • Lead off question - Delays to Crossrail (Supplementary) [7]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Simon, is there anything you want to add to that?
  • Lead off question - Delays to Crossrail (Supplementary) [13]

    • Question by: David Kurten
    • Meeting date: 06 September 2018
    David Kurten AM: Let us come back to the technical aspects. It seems the main problems are getting the three different signalling infrastructures to talk to each other. If you had an extension from Abbey Wood to Ebbsfleet then you would need Crossrail to go onto Southeastern track, which might be a fourth signalling structure. Would it not be? You are shaking your heads.
  • Mayor's manifesto commitments (Supplementary) [12]

    • Question by: Florence Eshalomi MP
    • Meeting date: 07 December 2016
    Florence Eshalomi AM: Good morning, Deputy Mayor. You may be aware that one of the things the Government was supposed to announce in the Autumn Statement was the whole announcement around the buy-as-you-go thought to help more people get on to the housing ladder. Do you think that would help in addressing the London housing crisis?
  • Future of the Metropolitan Police Service (Supplementary) [14]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 July 2016
    Florence Eshalomi AM: Thank you, Madam Chair. Good morning to you, Commissioner, and Mr Mayor. I just wanted to go back to some of the points raised by Assembly Member Bailey in terms of the night Tube. The first two lines are coming in in less than six weeks from today, and I am very happy that one of them will be going through my constituency, the Victoria line. I just wanted to go back to some of the points that you raised, Commissioner, in terms of the impact of the 24-hour licence, and this is an issue that has...
  • West London Tram

    • Reference: 2003/0220
    • Question by: Richard Barnes
    • Meeting date: 11 June 2003
    Will he make publicly available the questions asked by ORC International for the TfL opinion poll on the West London Tram released on the 20 March 2003? .
  • West London Tram

    • Reference: 2003/0221
    • Question by: Richard Barnes
    • Meeting date: 11 June 2003
    What is the current estimate for the total cost of the West London Tram? .
  • West London Tram

    • Reference: 2003/0222
    • Question by: Richard Barnes
    • Meeting date: 11 June 2003
    What negotiations have occurred between TfL and private sector companies over PFI financing for the West London Tram? .
  • West London Tram

    • Reference: 2003/0223
    • Question by: Richard Barnes
    • Meeting date: 11 June 2003
    Why has the decision on proceeding with the West London Tram been delayed until January 2004? .
  • Congestion Charge around Heathrow Airport

    • Reference: 2003/0224
    • Question by: Richard Barnes
    • Meeting date: 11 June 2003
    What negotiations have occurred between TfL and British Airports Authority over the introduction of a congestion charge around Heathrow Airport? .