Asked of 4

  • Lead off question - Delays to Crossrail (Supplementary) [3]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you for that. Will the decision to delay the opening until autumn next year [2019] ‑ it would be great to find out which month in autumn ‑ mean further delay in the opening of the other sections and the final full opening of the line in December 2019?
  • Lead off question - Delays to Crossrail (Supplementary) [7]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Simon, is there anything you want to add to that?
  • Lead off question - Delays to Crossrail (Supplementary) [13]

    • Question by: David Kurten
    • Meeting date: 06 September 2018
    David Kurten AM: Let us come back to the technical aspects. It seems the main problems are getting the three different signalling infrastructures to talk to each other. If you had an extension from Abbey Wood to Ebbsfleet then you would need Crossrail to go onto Southeastern track, which might be a fourth signalling structure. Would it not be? You are shaking your heads.
  • Youth engagement training for police officers

    • Reference: 2014/5003
    • Question by: Jenny Jones
    • Meeting date: 17 December 2014
    Will you take up the recommendations of the Met Challenge 2020 Youth Engagement report by Byron Grant which calls for the Metropolitan Police to provide skills sessions for police officers in how to communicate with young people?
  • Tube Strike Ballots - Minimum Support (Supplementary) [2]

    • Question by: Jennette Arnold OBE
    • Meeting date: 18 May 2011
    Ms Jones, you have a point of personal explanation?
  • CBRN attack

    • Reference: 2004/0377-1
    • Question by: Lynne Featherstone
    • Meeting date: 08 December 2004
    How many hospitals are equipped to treat victims of a CBRN attack, and what is your estimate of how many such victims can be accommodated? What is the capacity of the London Fire Brigade's Incident Response Units to decontaminate people who are exposed to a CBRN attack?
  • West London Tram

    • Reference: 2003/0220
    • Question by: Richard Barnes
    • Meeting date: 11 June 2003
    Will he make publicly available the questions asked by ORC International for the TfL opinion poll on the West London Tram released on the 20 March 2003? .
  • West London Tram

    • Reference: 2003/0221
    • Question by: Richard Barnes
    • Meeting date: 11 June 2003
    What is the current estimate for the total cost of the West London Tram? .
  • West London Tram

    • Reference: 2003/0222
    • Question by: Richard Barnes
    • Meeting date: 11 June 2003
    What negotiations have occurred between TfL and private sector companies over PFI financing for the West London Tram? .
  • West London Tram

    • Reference: 2003/0223
    • Question by: Richard Barnes
    • Meeting date: 11 June 2003
    Why has the decision on proceeding with the West London Tram been delayed until January 2004? .