Skip to main content
Mayor of London logo London Assembly logo
Home

Search questions

Filter results

Asked of 4

  • Lead off question - Delays to Crossrail (Supplementary) [3]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you for that. Will the decision to delay the opening until autumn next year [2019] ‑ it would be great to find out which month in autumn ‑ mean further delay in the opening of the other sections and the final full opening of the line in December 2019?
  • Lead off question - Delays to Crossrail (Supplementary) [7]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Simon, is there anything you want to add to that?
  • Lead off question - Delays to Crossrail (Supplementary) [13]

    • Question by: David Kurten
    • Meeting date: 06 September 2018
    David Kurten AM: Let us come back to the technical aspects. It seems the main problems are getting the three different signalling infrastructures to talk to each other. If you had an extension from Abbey Wood to Ebbsfleet then you would need Crossrail to go onto Southeastern track, which might be a fourth signalling structure. Would it not be? You are shaking your heads.
  • Tackling Homelessness in London

    • Reference: 2018/0231
    • Question by: Tom Copley
    • Meeting date: 18 January 2018
    How will the Mayor's 'No one needs to sleep rough in London' campaign and new London Homeless Charities Group contribute to reducing homelessness in the capital?
  • Vision for Old Oak Common (Supplementary) [1]

    • Question by: Caroline Russell
    • Meeting date: 07 September 2017
    Caroline Pidgeon MBE AM: Thank you. I have three specific questions I would like to ask you. To fulfil your vision, your modelling shows you are going to need a nursery in place by 2020 and another two years later. I am pleased you have made progress on this in your work. We are rapidly approaching 2018 now. Are you confident the funding is going to be in place and that they will be completed on time?
  • Vision for Old Oak Common (Supplementary) [5]

    • Question by: Tom Copley
    • Meeting date: 07 September 2017
    Tom Copley AM: Thank you very much, Chair. I wanted to ask you about the levels of affordable housing and specifically the London Affordable [Living] Rent which is the Mayor’s new form of tenure that is going to be benchmarked at social rent levels. Are you going to have a target specifically for London Affordable Rent across the OPDC site?
  • Tackling congestion in London

    • Reference: 2017/2836
    • Question by: Caroline Pidgeon
    • Meeting date: 13 July 2017
    Why does your draft Transport Strategy contain no proposals to change the Congestion Charge or bring in road pricing to tackle congestion?
  • Utilising Capacity at Airports in the South East.

    • Reference: 2015/2494
    • Question by: Caroline Pidgeon
    • Meeting date: 08 September 2015
    Given the extensive political opposition to a third runway at Heathrow and the inevitable legal and planning challenges that will arise it is almost certain expansion is unlikely to happen in the foreseeable future at Heathrow. In light of these realities do you believe sufficient attention has been given to improving surface transport to ensure that the significant spare air capacity at existing airports in the south east is fully utilised.
  • Local Government Asset Sales

    • Reference: 2015/2220
    • Question by: Tom Copley
    • Meeting date: 15 July 2015
    Given the Government's proposals to force London's local authorities to sell high value assets, do you think the revenue generated should be hypothecated for building homes in the capital?
  • Devolution of rail services

    • Reference: 2015/1238
    • Question by: Caroline Pidgeon
    • Meeting date: 21 May 2015
    What discussions have you had with the Department for Transport on the further devolution of suburban rail services to Transport for London?