Asked of 3

  • Lead off question - Delays to Crossrail (Supplementary) [3]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you for that. Will the decision to delay the opening until autumn next year [2019] ‑ it would be great to find out which month in autumn ‑ mean further delay in the opening of the other sections and the final full opening of the line in December 2019?
  • Lead off question - Delays to Crossrail (Supplementary) [7]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Simon, is there anything you want to add to that?
  • Lead off question - Delays to Crossrail (Supplementary) [13]

    • Question by: David Kurten
    • Meeting date: 06 September 2018
    David Kurten AM: Let us come back to the technical aspects. It seems the main problems are getting the three different signalling infrastructures to talk to each other. If you had an extension from Abbey Wood to Ebbsfleet then you would need Crossrail to go onto Southeastern track, which might be a fourth signalling structure. Would it not be? You are shaking your heads.
  • Dissolution of LFEPA (Supplementary) [1]

    • Question by: Fiona Twycross
    • Meeting date: 02 December 2015
    Fiona Twycross AM: I wanted to correct the impression that was given that the way it has been operating at the moment has been simply about opposition Members [on LFEPA] getting at the Mayor. The fact is that the Mayor has insisted on managing by Direction even when there has not been an impasse, including on issues over which there has been cross‑party agreement by LFEPA Members. I just wondered if you could focus a little bit on what impact the Mayor’s insistence on management by Direction has had. To be honest, we have had Directions on all sorts of...
  • Dissolution of LFEPA (Supplementary) [2]

    • Question by: Richard Tracey
    • Meeting date: 02 December 2015
    Richard Tracey AM: Chairman, probably this is one for you as the politician of the two of you. The fact is, surely, that government, particularly local government, has been changing very considerably over recent years. That is accepted. The straight point to you: is it not correct that perhaps LFEPA in its current form is out of date and past its sell‑by date, really?
  • New Technology (Supplementary) [4]

    • Question by: Fiona Twycross
    • Meeting date: 02 December 2015
    Fiona Twycross AM: We obviously have to make sensible use of resources in the face of cuts. Some of the new technology that could come online is really interesting and will offer exciting possibilities, but do you agree with the Londoner who contacted me yesterday to say that £283,000 for a website rebuild is bordering on scandalous?
  • Leveson Inquiry

    • Reference: 2012/0068-2
    • Question by: Joanne McCartney
    • Meeting date: 20 December 2012
    Does the Metropolitan Police Service actually accept in broad principle the findings of the Leveson Inquiry?
  • Operation Condor

    • Reference: 2012/0071-2
    • Question by: Roger Evans
    • Meeting date: 20 December 2012
    Yes, we have just got a few questions about Operation Condor, and I think my colleague, Andrew, has some questions about this as well. Deputy Commissioner, you recently carried out the operation in my corner of town in Havering and Redbridge, I think you arrested one person in Havering and nobody in Redbridge. How do you judge the impact of a large-scale operation like that against the resource costs?
  • Leveson Inquiry (Supplementary) [1]

    • Question by: Tony Arbour
    • Meeting date: 20 December 2012
    Tony Arbour (AM): Do you have any views on that, Stephen?
  • Leveson Inquiry (Supplementary) [2]

    • Question by: Joanne McCartney
    • Meeting date: 20 December 2012
    Obviously because the time has slipped for getting bids in to you by the end of February but the schemes are going to be starting in April, the new financial year, it does not give them very much leeway. Will you be giving them some extra leeway in how they can deliver those schemes?