Skip to main content
Mayor of London logo London Assembly logo
Home

Search questions

Filter results

Asked of 2

  • Key Challenges for the London Fire Brigade (Supplementary) [2]

    • Question by: Susan Hall
    • Meeting date: 08 February 2018
    Susan Hall AM: Thank you. Good morning, both. Fiona, massive congratulations to you. In your opening statement, you said that we are very proud of the Brigade and of course we are, and we were very happy on this side that Mayor Khan decided to do three different reports to see how well the service was doing, given the closure of the stations. Of course, it came out that the LFB was in a very good place and so we were very happy about that. When will you publish the new corporate governance arrangements prior to the abolition of the...
  • Key Challenges for the London Fire Brigade (Supplementary) [12]

    • Question by: Tony Devenish
    • Meeting date: 08 February 2018
    Tony Devenish AM: Good morning, Deputy Mayor. If we tried to paint a picture of the LFB in, say, eight years, 2026, could you paint me some big pictures of what the real differences will be, please?
  • Potential for Further Budget Increases (Supplementary) [3]

    • Question by: Bob Neill
    • Meeting date: 25 April 2007
    Does that include taking advice from the people on Lord James of Blackheath's team who had to bail out some of the consequences of the Dome? The police were involved in that.
  • Potential for Further Budget Increases (Supplementary) [5]

    • Question by: Bob Neill
    • Meeting date: 25 April 2007
    The trouble that I have is that the more one departs from basic commercial practice, when we fall into public sector practice, the greater the risk, history tells us, of budget overruns.
  • Potential for Further Budget Increases (Supplementary) [7]

    • Question by: Bob Neill
    • Meeting date: 25 April 2007
    Can I come, Sir Roy, back to a point that Mr Higgins made in relation to our earlier discussions? I am concerned about the extent to which bottom up budgeting is really being regarded as being acceptable at all. Would you not accept that one of the lessons I think that we have learned from projects like the Dome and other public sector projects is that, by and large, you should start from the revenue generation figure, and be very reluctant about bottom up budgeting, because that is where you get `creep'? If you have the revenue regeneration figure as...
  • Potential for Further Budget Increases (Supplementary) [8]

    • Question by: Richard Barnes
    • Meeting date: 25 April 2007
    How great is the budget for this security process, during the build phase of the building site?
  • Potential for Further Budget Increases (Supplementary) [9]

    • Question by: Bob Neill
    • Meeting date: 25 April 2007
    ): I am grateful for that. When we looked at past history, things like Wembley and the Dome, one thing which tended to cause further increases in budgets was, regrettably, elements of fraud, sometimes sub-contractor fraud, and a lack of control over sub-contractor costs. What lessons have we learnt? What systems are being put in place to bear down upon that in a way which did not happen, perhaps, in some of those other projects?
  • Potential for Further Budget Increases (Supplementary) [10]

    • Question by: Richard Barnes
    • Meeting date: 25 April 2007
    So, at this moment, the total budgeting costs for security are approximately £1.4 billion then, if one conflates the two figures?
  • Potential for Further Budget Increases (Supplementary) [11]

    • Question by: Richard Barnes
    • Meeting date: 25 April 2007
    Yes, but on top of that is the £600 million for the Metropolitan Police?
  • Potential for Further Budget Increases (Supplementary) [12]

    • Question by: Brian Coleman
    • Meeting date: 25 April 2007
    But then you add the £600 million on top and you get £1,400 million?