  • Lead off question - Delays to Crossrail (Supplementary) [2]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Mr Mayor, on 25 July there was an item on Crossrail in the private section of the TfL Board, which you chair, as well as the public section. Were any concerns raised? As Simon has outlined, the programme is building up and you are getting concerned. Were any concerns raised there about the possibility of delay in the opening?
  • Lead off question - Delays to Crossrail (Supplementary) [4]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Finally, time is money in the construction sector. There will inevitably be an additional cost with this delay. Who is going to be picking up that bill, is it TfL and Londoners or is it going to be the DfT?
  • Lead off question - Delays to Crossrail (Supplementary) [5]

    • Question by: Gareth Bacon MP
    • Meeting date: 06 September 2018
    Gareth Bacon AM: This is to the Commissioner, Mr Brown. What are the financial implications of this?
  • Lead off question - Delays to Crossrail (Supplementary) [8]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Mike, obviously there are still major ambitions in TfL’s finances and the TfL budget in terms of Crossrail 2. TfL has said it will be able to pay for half of Crossrail 2. Do you think this would still be the case, given we are seeing a delay in Crossrail 1?
  • Lead off question - Delays to Crossrail (Supplementary) [11]

    • Question by: Caroline Russell
    • Meeting date: 06 September 2018
    Caroline Russell AM: OK. I am going to ask Mike now. The status quo on Oxford Street is not OK. We know that urgent attention is needed to deal even with the current overcrowding, let alone with the overcrowding that will come from the new Crossrail passengers. Has TfL done a Healthy Streets check on Oxford Street in its current condition, and if not, will you?
  • Legacy

    • Reference: 2009/0117-1
    • Question by: Dee Doocey
    • Meeting date: 21 October 2009
    Do you believe that your employment targets for local people will provide the legacy that was promised in Singapore?
  • Living Wage

    • Reference: 2009/0115-1
    • Question by: Jenny Jones
    • Meeting date: 21 October 2009
    Is it acceptable that around 300 workers on the Olympic Park construction sites are receiving poverty pay?
  • Living Wage (Supplementary) [3]

    • Question by: Richard Tracey
    • Meeting date: 21 October 2009
    Could I take up one point with you on the whole relative costs of salaries and so on? Mr Higgins, you, I think, serve with seven other directors on the ODA, receiving pretty substantial salaries. Indeed, I believe you, this last year, did forego half of your bonus until 2012. Would it be reasonable for you and your fellow directors to consider foregoing your complete bonus until you have finished the job, and then receive whatever you are entitled to, through the success you have achieved?
  • Living Wage (Supplementary) [4]

    • Question by: Richard Barnbrook
    • Meeting date: 21 October 2009
    ): I am happy to hear that we are actually on track with this and so the rumours I have been hearing that we are six to eight months behind have obviously been expelled by yourselves by saying we are actually on track, financially and work-wise. One thing I do have a concern with - and I have to follow other Members here - is the Living Wage or at least working wage of the London weighting. What I would like to have spelt out clearly is you are suggesting, by this time, October 2010, there will be 10,000 workers...
  • Living Wage (Supplementary) [5]

    • Question by: Jenny Jones
    • Meeting date: 21 October 2009
    Thank you very much. I am very glad to hear that you have made progress on that because it is incredibly important. Congratulations on being on time and on budget. That is pretty amazing and I am sure we are all happy about that. One of the next steps that you could do, in fact, with the Living Wage, is to have accreditation from London Citizens and I gather that organisations like the London Development Agency (LDA) already do have that. I wondered if you would take that next step and get accreditation and then, perhaps, you could also work...