  • Olympics Park and Venues (Supplementary) [1]

    • Question by: Darren Johnson
    • Meeting date: 25 April 2007
    So you are guaranteeing that we are seeing no reduction whatsoever in the amount of public open space?
  • Olympics Park and Venues (Supplementary) [2]

    • Question by: Darren Johnson
    • Meeting date: 25 April 2007
    So the other pieces of public open space which are not contained in this application will be in other applications or have been agreed already?
  • Olympics Park and Venues (Supplementary) [8]

    • Question by: Darren Johnson
    • Meeting date: 25 April 2007
    Thank you. David [Higgins] mentioned the size of the Park earlier, but the new planning application does reduce the amount of open space in the Park by the equivalent of 34 football pitches, from 127 hectares to 109 hectares. The application is smaller than the previous one. We are getting a smaller park are we not?
  • Olympics Park and Venues (Supplementary) [9]

    • Question by: Darren Johnson
    • Meeting date: 25 April 2007
    OK, thanks. If I can briefly move on now to sustainability standards? Last month the Mayor told us that now the budget had been agreed, we can expect improvements in the environmental standards for the Olympics. What changes will be made now that you have the money in the budget?
  • Olympics Park and Venues

    • Reference: 2007/0024-1
    • Question by: Darren Johnson
    • Meeting date: 25 April 2007
    Planned expenditure on the park and venues has risen from £2.4bn to £3.1bn in the last two years. What long-term benefits will Londoners see as a result of this extra money?