  • Lead off question - Delays to Crossrail (Supplementary) [1]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you. Mr Mayor, just ten weeks ago, in answer to a Mayoral question (MQ), you stated, “The Elizabeth line remains on course to open as planned in December 2018”. The Commissioner, in the TfL Board report of 25 July [2018] stated, “Crossrail remains on course to open as planned in December”. Sir Terry, on 6 June, when the Transport Committee visited Tottenham Court Road with you, you gave me an absolute assurance that the opening of Crossrail would be in December. You even confirmed the date, Sunday, 9 December when the Queen would be opening...
  • Lead off question - Delays to Crossrail (Supplementary) [6]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Thank you. To come back to Crossrail, on this side [of the table] we definitely recognise the scale of this project but once completed it will be a big success for London. I am definitely looking forward to when it opens. You may be aware of Rob Holden’s [CBE, Chairman, High Speed 1] letter last week in The Times where he stated, “The problems with Crossrail arose from the decision taken in 2011 to delay the procurement of new rolling stock, a decision that has affected the commissioning of those new trains ... signalling was always going...
  • Lead off question - Delays to Crossrail (Supplementary) [9]

    • Question by: Caroline Russell
    • Meeting date: 06 September 2018
    Caroline Russell AM: Thank you, Chairman. I want to ask about the experience of the passengers who are waiting to use this line but before I get on to those questions I want to pick up on something that Sir Terry said at the very beginning. You said, “We mitigated one risk and others materialised”. I wonder if you could expand on that a bit more, whether that is what has caused this decision about the delay.
  • Lead off question - Delays to Crossrail (Supplementary) [14]

    • Question by: Keith Prince
    • Meeting date: 06 September 2018
    Keith Prince AM: Thank you, Chairman. Good morning, Sir Terry. I am trying to get some dates straight in my head. You mentioned a Board meeting in July [2018] where it was raised that there could be problems. Could you tell me the date of that meeting in July, please?
  • Evacuation and care of Schoolchildren (Supplementary) [2]

    • Question by: Elizabeth Howlett
    • Meeting date: 08 December 2004
    David Wechsler added:
  • Provisions for continued water supply (Supplementary) [1]

    • Question by: Roger Evans
    • Meeting date: 08 December 2004
    Is all the alternative supply through the mains, or are you looking at making mobile supplies available or bottled water available?
  • Provisions for continued water supply (Supplementary) [2]

    • Question by: Roger Evans
    • Meeting date: 08 December 2004
    I was just looking back at Mr Wechsler's answer to the question on water supplies. He talks about a utilities sub-committee for London that was looking at dealing with this problem. Does that committee include representation from suppliers other than Thames Water, because certainly those of us in outer London often have our supplies from other organisations? I live in Romford. I get my supply from Anglian Water.
  • Provisions for continued water supply (Supplementary) [3]

    • Question by: Roger Evans
    • Meeting date: 08 December 2004
    If we were to, for whatever reason, lose a large amount of Thames Water supply, would they be called on to fill that gap, and would they have the capacity to be able to do that?
  • Operational planning with non-London local authorities (Supplementary) [1]

    • Question by: Bob Neill
    • Meeting date: 08 December 2004
    I notice that the surrounding county councils, of course, are the responsible authority for civil defence and emergency planning. Do you think perhaps it is an advantage that they are able to plan at a county, as opposed to a borough, level? Is that something you should learn from London's point of view? Secondly, I also note that the very helpful plans, which you have detailed, Mr Wechsler, are made available to the public, both on, for example, Oxfordshire County Council's website and Surrey County Council's website, and that Surrey, indeed, has a dedicated SurreyAlert website. Do we propose to...
  • Operational planning with non-London local authorities (Supplementary) [2]

    • Question by: Bob Neill
    • Meeting date: 08 December 2004
    I just wondered if people might more logically think we would go to a London alert website, rather than a Bexley alert or a Hammersmith alert.