  • Budget and Venues Update (Supplementary) [3]

    • Question by: Peter Hulme Cross
    • Meeting date: 10 November 2007
    Mr Higgins, you just mentioned the site. You said it was 'highly contaminated'. Those were your words. Now, in marked contrast to your brochure of photographs here, I have got some photographs which actually show the contractors at work. They are digging up, if that is the right phrase, a whole lot of dust which is blowing over the surrounding countryside and the surrounding residential areas. If that site is highly contaminated, don't you think that enormous efforts should be made to damp down the dust and make sure that the dust does not go onto surrounding areas?
  • Budget and Venues Update (Supplementary) [21]

    • Question by: Peter Hulme Cross
    • Meeting date: 10 November 2007
    Are you aware that there is a suspicion that there might be radioactive waste on the site? There were two instances I have come across. One was dumped in 1959 and another was dumped in 1953 and in both instances they say that the waste was possibly radioactive.
  • Budget and Venues Update (Supplementary) [23]

    • Question by: Peter Hulme Cross
    • Meeting date: 10 November 2007
    I attended the meeting in Hackney Wick about a couple of weeks ago when people were actually complaining about the dust that was flying around, particularly over the Clays Lane Estate and in that general area. People actually said, 'Having inhaled this dust I felt a real sore throat and burning eyes and burning lips,' and people were coming up to me after the meeting saying, 'Can you do anything about this?' I felt that there was a real concern. Now I know that there has been quite a lot of contamination on that site. I have documents here which...
  • Budget and Venues Update (Supplementary) [31]

    • Question by: Peter Hulme Cross
    • Meeting date: 10 November 2007
    Alright, and your contractors, those people who are actually working on the site, driving these vehicles and what have you, are they properly protected, using properly protective clothing and all the rest?
  • Budget and Venues Update (Supplementary) [36]

    • Question by: Peter Hulme Cross
    • Meeting date: 10 November 2007
    Alright, are you aware that the River Lee has been tested for radioactivity and in fact I have a Capita Symonds document here which says, `That the levels were slightly higher than expected, not high enough to cause great concern,' and identifies, `Elevated levels of radioactivity above levels considered to be natural background level for the area'.
  • Potential for Further Budget Increases (Supplementary) [1]

    • Question by: Damian Hockney
    • Meeting date: 25 April 2007
    Sir Roy, how much of the £500 million construction contingency has so far been earmarked to be spent? There has been a lot of talk about this and a lot of rumours in the industry.
  • Potential for Further Budget Increases (Supplementary) [2]

    • Question by: Damian Hockney
    • Meeting date: 25 April 2007
    My only point really on this is that it is in that area where costs can so easily run away. In the industry, there are rumours; you speak to any of the major contractors or the journalists in the area, and they will tell you that £350 million of the £500 million has so far been earmarked, and that insiders within the ODA have told them this.
  • Potential for Further Budget Increases (Supplementary) [4]

    • Question by: Damian Hockney
    • Meeting date: 25 April 2007
    So it will not go to CLM (CH2M Hill International, Laing O'Rourke, Mace)? They will not be the people who will do it?
  • Potential for Further Budget Increases (Supplementary) [6]

    • Question by: Damian Hockney
    • Meeting date: 25 April 2007
    The fact that so few people appear to have tendered for the Aquatic Centre does that not concern you in terms of possibilities?
  • Potential for Further Budget Increases (Supplementary) [14]

    • Question by: Damian Hockney
    • Meeting date: 25 April 2007
    So if that £500 million contingency can last up to the end of next year, then how much more of the overall contingency budget that the Government has aside, which has been the cause of so much controversy, do you think you will need?