  • Lead off question - Delays to Crossrail (Supplementary) [3]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you for that. Will the decision to delay the opening until autumn next year [2019] ‑ it would be great to find out which month in autumn ‑ mean further delay in the opening of the other sections and the final full opening of the line in December 2019?
  • Lead off question - Delays to Crossrail (Supplementary) [7]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Simon, is there anything you want to add to that?
  • Lead off question - Delays to Crossrail (Supplementary) [13]

    • Question by: David Kurten
    • Meeting date: 06 September 2018
    David Kurten AM: Let us come back to the technical aspects. It seems the main problems are getting the three different signalling infrastructures to talk to each other. If you had an extension from Abbey Wood to Ebbsfleet then you would need Crossrail to go onto Southeastern track, which might be a fourth signalling structure. Would it not be? You are shaking your heads.
  • Flooding Action Plan

    • Reference: 2015/3751
    • Question by: Steve O'Connell
    • Meeting date: 18 November 2015
    What changes do you anticipate to the London Plan or other planning guidance as a result of your new action plan to help tackle flooding risks in London?
  • Starter Homes

    • Reference: 2015/3301
    • Question by: Steve O'Connell
    • Meeting date: 21 October 2015
    How will you be taking forward the Government's recent announcement to enable the delivery of Starter Homes in London?
  • Sutton Transport Improvements

    • Reference: 2015/0402
    • Question by: Steve O'Connell
    • Meeting date: 21 January 2015
    In December you visited The Institute of Cancer Research in Belmont, where you made clear that you strongly supported the plans to expand to become the second biggest campus of its kind in the world. What effect will these plans have on the business case for the Sutton Tram Extension?
  • Legacy

    • Reference: 2009/0117-1
    • Question by: Dee Doocey
    • Meeting date: 21 October 2009
    Do you believe that your employment targets for local people will provide the legacy that was promised in Singapore?
  • Living Wage

    • Reference: 2009/0115-1
    • Question by: Jenny Jones
    • Meeting date: 21 October 2009
    Is it acceptable that around 300 workers on the Olympic Park construction sites are receiving poverty pay?
  • Living Wage (Supplementary) [3]

    • Question by: Richard Tracey
    • Meeting date: 21 October 2009
    Could I take up one point with you on the whole relative costs of salaries and so on? Mr Higgins, you, I think, serve with seven other directors on the ODA, receiving pretty substantial salaries. Indeed, I believe you, this last year, did forego half of your bonus until 2012. Would it be reasonable for you and your fellow directors to consider foregoing your complete bonus until you have finished the job, and then receive whatever you are entitled to, through the success you have achieved?
  • Living Wage (Supplementary) [4]

    • Question by: Richard Barnbrook
    • Meeting date: 21 October 2009
    ): I am happy to hear that we are actually on track with this and so the rumours I have been hearing that we are six to eight months behind have obviously been expelled by yourselves by saying we are actually on track, financially and work-wise. One thing I do have a concern with - and I have to follow other Members here - is the Living Wage or at least working wage of the London weighting. What I would like to have spelt out clearly is you are suggesting, by this time, October 2010, there will be 10,000 workers...