Asked of 1

  • Legacy (Supplementary) [7]

    • Question by: Jennette Arnold OBE
    • Meeting date: 25 April 2007
    It is just a quick one. I understand that the delay at Hog Hill has been caused by you finding a particular wildlife there that needs to be preserved, and there has been six months delay to date. Can you guarantee us that it will not be a year's delay or 18 months' delay? Where are we with that?
  • Legacy (Supplementary) [16]

    • Question by: Jennette Arnold OBE
    • Meeting date: 25 April 2007
    So it has been sorted now and it will be finished by September? That is what you are saying?
  • Legacy (Supplementary) [18]

    • Question by: Jennette Arnold OBE
    • Meeting date: 25 April 2007
    So the newts will be rehoused?
  • Contingency (Supplementary) [4]

    • Question by: Murad Qureshi
    • Meeting date: 25 April 2007
    Finally, given that you have milestones and key milestones and a set date to achieve it, would it not have been better to have set up bonus payments rather than contingency sums, given that is going to be the name of the game - getting to key stages at key times at critical points? Clearly we would rather be giving them money for achieving that, rather than spending their time making those claims, which invariably half the building trade does.
  • Contingency (Supplementary) [5]

    • Question by: Murad Qureshi
    • Meeting date: 25 April 2007
    Sir Roy, if we accept the Government figures as the upper limits to the expenditure on the Olympics, I think the key thing is the management of the contingencies. I am worried that we find ourselves in contracts with contractors who then spend most of their time making claims for the contingencies. They are very generous; about 60% of the build costs. I have certainly had that experience of managing projects myself. What do you have lined up in the procurement arrangements with contractors which make sure they focus and achieve the milestones, rather than putting in the estimators to...
  • Contingency (Supplementary) [9]

    • Question by: Murad Qureshi
    • Meeting date: 25 April 2007
    You have mentioned the Cabinet Committees that are keeping an eye on this. Surely the building contract and the legality of that will supersede anything that they can decide about which contingency sums can be drawn from or not.
  • Infrastrucutre and Regeneration (Supplementary) [3]

    • Question by: Jennette Arnold OBE
    • Meeting date: 25 April 2007
    I want to go back to jobs and I want to talk about the jobs that are your responsibility. Can you confirm for us the total amount of jobs projected? I was present at a recent presentation by your excellent Head of HR which really electrified the room, local communities, and put meat around the skeleton of the plans. I would like you to confirm with us here today the absolute numbers that you are expecting to employ. I also understand that you have employed - is it your first 500 or 5,000 people? I saw something printed this week...