  • Lead off question - Delays to Crossrail (Supplementary) [3]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you for that. Will the decision to delay the opening until autumn next year [2019] ‑ it would be great to find out which month in autumn ‑ mean further delay in the opening of the other sections and the final full opening of the line in December 2019?
  • Lead off question - Delays to Crossrail (Supplementary) [7]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Simon, is there anything you want to add to that?
  • Lead off question - Delays to Crossrail (Supplementary) [13]

    • Question by: David Kurten
    • Meeting date: 06 September 2018
    David Kurten AM: Let us come back to the technical aspects. It seems the main problems are getting the three different signalling infrastructures to talk to each other. If you had an extension from Abbey Wood to Ebbsfleet then you would need Crossrail to go onto Southeastern track, which might be a fourth signalling structure. Would it not be? You are shaking your heads.
  • Dissolution of LFEPA (Supplementary) [1]

    • Question by: Fiona Twycross
    • Meeting date: 02 December 2015
    Fiona Twycross AM: I wanted to correct the impression that was given that the way it has been operating at the moment has been simply about opposition Members [on LFEPA] getting at the Mayor. The fact is that the Mayor has insisted on managing by Direction even when there has not been an impasse, including on issues over which there has been cross‑party agreement by LFEPA Members. I just wondered if you could focus a little bit on what impact the Mayor’s insistence on management by Direction has had. To be honest, we have had Directions on all sorts of...
  • Dissolution of LFEPA (Supplementary) [2]

    • Question by: Richard Tracey
    • Meeting date: 02 December 2015
    Richard Tracey AM: Chairman, probably this is one for you as the politician of the two of you. The fact is, surely, that government, particularly local government, has been changing very considerably over recent years. That is accepted. The straight point to you: is it not correct that perhaps LFEPA in its current form is out of date and past its sell‑by date, really?
  • New Technology (Supplementary) [4]

    • Question by: Fiona Twycross
    • Meeting date: 02 December 2015
    Fiona Twycross AM: We obviously have to make sensible use of resources in the face of cuts. Some of the new technology that could come online is really interesting and will offer exciting possibilities, but do you agree with the Londoner who contacted me yesterday to say that £283,000 for a website rebuild is bordering on scandalous?
  • Priorities for the Coming Year (Supplementary) [5]

    • Question by: Murad Qureshi
    • Meeting date: 10 November 2007
    Just going on from John's [Biggs] friendly question, you outlined many, many priorities for next year and, if anything, the first observation is maybe there are too many. Can you possibly lose focus as a result and what kind of managerial systems have you got to make sure that you can cover all the ground? For example, the two additional ones that I had were implementing the Mayor's Housing Strategy and the sporting provision and the youth service. Now those are clearly new areas on top of your Olympic responsibilities, as well as the climate change work.
  • London City Airport (Supplementary) [5]

    • Question by: Geoff Pope
    • Meeting date: 10 November 2007
    Can you say anything about the timescale of this application?