Asked of 3

  • London Recovery Board and London Transition Board (Supplementary) [21]

    • Question by: Susan Hall
    • Meeting date: 02 July 2020
    Susan Hall AM: Thank you, Chair. This is to Mary [Harpley]. I am sorry if the precise figure was mentioned earlier but I did not catch it if it was. Niran [Mothada] specifically referred to the commitment to the Green New Deal. If I recall, the Mayor put aside or committed £50 million to it at the last minute in the budget in February. Can you confirm what level of funding you are looking at for this at the moment given our uncertain finances, please?
  • Temporary Venues

    • Reference: 2009/0122-1
    • Question by: Andrew Boff
    • Meeting date: 21 October 2009
    To what extent have LOCOG been successful in ensuring value for money and adequate public consultation in relation to temporary venues?
  • Risks

    • Reference: 2009/0116-1
    • Question by: John Biggs
    • Meeting date: 21 October 2009
    What are your top three greatest risks and how are you managing these, and what is your greatest reputational risk?
  • Living Wage (Supplementary) [2]

    • Question by: Murad Qureshi
    • Meeting date: 21 October 2009
    Murad Qureshi (AM): I just want to continue on Richard Tracey's theme, actually, and I think it is a major reputational risk for the ODA, quite honestly, these whole bonuses that you have been giving yourselves. I just want to be clear; how can the ODA possibly justify raking in £2.6 million in salaries and bonuses when there is a funding shortfall for the Olympic sports' venues themselves, and the land assembly in particular?
  • Temporary Venues (Supplementary) [1]

    • Question by: Gareth Bacon MP
    • Meeting date: 21 October 2009
    I am going to focus in on Greenwich, which, I am sure you are both aware, is becoming a slightly controversial area. A quick opening question: in the bid book the estimated cost for the temporary venues in Greenwich Park was £8.8 million. What is the current estimated cost?
  • Olympic Village and Legacy

    • Reference: 2008/0009-1
    • Question by: Andrew Boff
    • Meeting date: 08 October 2008
    What are the latest plans for the Olympic Village and how do you see its legacy?
  • Lessons Learned from the Beijing Olympic Games

    • Reference: 2008/0010-1
    • Question by: John Biggs
    • Meeting date: 08 October 2008
    What lessons has the ODA learned from the Beijing Games?
  • Olympic Security Budget

    • Reference: 2008/0011-1
    • Question by: Dee Doocey
    • Meeting date: 08 October 2008
    Are you concerned that the budget for Olympic security has not yet been agreed by the Home Office?
  • Olympic Village

    • Reference: 2008/0008-1
    • Question by: Darren Johnson
    • Meeting date: 08 October 2008
    What new options for the funding, design, and housing provision of the Olympic Village are now being explored, in the light of the current economic climate and housing market conditions?
  • Opening Statement

    • Reference: 2008/0110-1
    • Question by: Jennette Arnold OBE
    • Meeting date: 08 October 2008
    Good morning Members. We welcome John Armitt and David Higgs who are here with us this morning and we are looking forward to a good exchange of information. Thank you both for coming. Before I go on, can I just say that I was asked by the Olympic Delivery Authority (ODA) to circulate a booklet which you will have found on your seats and John [Armitt] or David [Higgins] will make reference to this booklet in answer to Mr Boff's question [see Appendix 2]. The Deputy Chair and I had a pre-meeting with both John and David and we agreed...