Skip to main content
Mayor of London logo London Assembly logo
Home

Search questions

Filter results

Asked of 3

  • Lead off question - Delays to Crossrail (Supplementary) [3]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you for that. Will the decision to delay the opening until autumn next year [2019] ‑ it would be great to find out which month in autumn ‑ mean further delay in the opening of the other sections and the final full opening of the line in December 2019?
  • Lead off question - Delays to Crossrail (Supplementary) [7]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Simon, is there anything you want to add to that?
  • Lead off question - Delays to Crossrail (Supplementary) [13]

    • Question by: David Kurten
    • Meeting date: 06 September 2018
    David Kurten AM: Let us come back to the technical aspects. It seems the main problems are getting the three different signalling infrastructures to talk to each other. If you had an extension from Abbey Wood to Ebbsfleet then you would need Crossrail to go onto Southeastern track, which might be a fourth signalling structure. Would it not be? You are shaking your heads.
  • Priorities for the Coming Year (Supplementary) [5]

    • Question by: Murad Qureshi
    • Meeting date: 10 November 2007
    Just going on from John's [Biggs] friendly question, you outlined many, many priorities for next year and, if anything, the first observation is maybe there are too many. Can you possibly lose focus as a result and what kind of managerial systems have you got to make sure that you can cover all the ground? For example, the two additional ones that I had were implementing the Mayor's Housing Strategy and the sporting provision and the youth service. Now those are clearly new areas on top of your Olympic responsibilities, as well as the climate change work.
  • London City Airport (Supplementary) [5]

    • Question by: Geoff Pope
    • Meeting date: 10 November 2007
    Can you say anything about the timescale of this application?
  • Living wage (Supplementary) [2]

    • Question by: Darren Johnson
    • Meeting date: 08 September 2005
    Finally, you mentioned as well that it is not just about tackling the issue of low pay here, but it is making sure that people are paid a decent wage for all work done in relation to the Olympics. Therefore, in terms of merchandise being imported and so on, will you be making sure that there are guarantees that that is not through sweatshop labour, and that there are principles of fair trade, fair pay, and so on incorporated into that?
  • Olympic Organisations (Supplementary) [7]

    • Question by: Bob Blackman
    • Meeting date: 08 September 2005
    Would you not agree with the me that, actually, the approach to take now is to sweep away this bureaucracy and have exactly what you have said: a simple organisation that everyone can understand, so if things go wrong, we know who to look to, rather than it being obscured all over the place?
  • Olympic Organisations (Supplementary) [9]

    • Question by: Bob Blackman
    • Meeting date: 08 September 2005
    There are not going to be. Okay, fine.
  • Local Community Interests (Supplementary) [7]

    • Question by: John Biggs
    • Meeting date: 08 September 2005
    I think I meant London citizens in lower case, rather than that particular organisation.
  • Outer London Boroughs (Supplementary) [2]

    • Question by: Murad Qureshi
    • Meeting date: 08 September 2005
    I am glad to hear that, and I suspect a lot of local authorities will be competing amongst themselves for which countries to host. Could you just keep me informed about those developments, because it is quite a critical one that we need to keep an eye on.