Asked of 1

  • Vision for Old Oak Common (Supplementary) [2]

    • Question by: Joanne McCartney
    • Meeting date: 07 September 2017
    Joanne McCartney AM: Thank you. I want to ask about the National Audit Office (NAO) report last year. It was reported in that report that the DfT had asked HS2 to assess the impact of extending the timetable for phase one up to 12 months. I am just wondering what impact that would have on your development schedule?
  • Vision for Old Oak Common (Supplementary) [4]

    • Question by: Len Duvall OBE
    • Meeting date: 07 September 2017
    Len Duvall AM: Can we go back to the Crossrail depot? Do you both agree with Sir Terry Farrell’s [British architect] comments when he says the failure to plan to deck over the Crossrail depot represents London’s worst cock-up in 50 years?