  • Lead off question - Delays to Crossrail (Supplementary) [1]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you. Mr Mayor, just ten weeks ago, in answer to a Mayoral question (MQ), you stated, “The Elizabeth line remains on course to open as planned in December 2018”. The Commissioner, in the TfL Board report of 25 July [2018] stated, “Crossrail remains on course to open as planned in December”. Sir Terry, on 6 June, when the Transport Committee visited Tottenham Court Road with you, you gave me an absolute assurance that the opening of Crossrail would be in December. You even confirmed the date, Sunday, 9 December when the Queen would be opening...
  • Lead off question - Delays to Crossrail (Supplementary) [6]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Thank you. To come back to Crossrail, on this side [of the table] we definitely recognise the scale of this project but once completed it will be a big success for London. I am definitely looking forward to when it opens. You may be aware of Rob Holden’s [CBE, Chairman, High Speed 1] letter last week in The Times where he stated, “The problems with Crossrail arose from the decision taken in 2011 to delay the procurement of new rolling stock, a decision that has affected the commissioning of those new trains ... signalling was always going...
  • Lead off question - Delays to Crossrail (Supplementary) [9]

    • Question by: Caroline Russell
    • Meeting date: 06 September 2018
    Caroline Russell AM: Thank you, Chairman. I want to ask about the experience of the passengers who are waiting to use this line but before I get on to those questions I want to pick up on something that Sir Terry said at the very beginning. You said, “We mitigated one risk and others materialised”. I wonder if you could expand on that a bit more, whether that is what has caused this decision about the delay.
  • Lead off question - Delays to Crossrail (Supplementary) [14]

    • Question by: Keith Prince
    • Meeting date: 06 September 2018
    Keith Prince AM: Thank you, Chairman. Good morning, Sir Terry. I am trying to get some dates straight in my head. You mentioned a Board meeting in July [2018] where it was raised that there could be problems. Could you tell me the date of that meeting in July, please?
  • Notification procedures for mass evacuation

    • Reference: 2004/0409-1
    • Question by: Angie Bray
    • Meeting date: 08 December 2004
    What are the notification procedures for mass evacuation? Have these been tested?
  • 2nd London Safety Plan

    • Reference: 2004/0412-1
    • Question by: Angie Bray
    • Meeting date: 08 December 2004
    What implications for resilience in Central London do the proposals in the draft 2nd London Safety Plan have?
  • Private sector

    • Reference: 2004/0372-1
    • Question by: Dee Doocey
    • Meeting date: 08 December 2004
    Are you satisfied that businesses in London have adequate plans in place to cope with a major incident; what steps are being taken to spread best practice advice on planning for an emergency amongst the private sector, and how much co-operation has there been from business to date?
  • Lines of accountability

    • Reference: 2004/0378-1
    • Question by: Graham Tope
    • Meeting date: 08 December 2004
    Who is ultimately in charge in the event of a terrorist attack or a major incident in London, including managing the immediate aftermath and longer-term recovery?
  • Planning & training

    • Reference: 2004/0379-1
    • Question by: Graham Tope
    • Meeting date: 08 December 2004
    When was the last training exercise involving all the emergency services in London held? How are boroughs included in such exercises? For what range of scenarios has planning and training taken place, and have these included scenarios in outer London?
  • Emergency services staffing

    • Reference: 2004/0383-1
    • Question by: Mike Tuffrey
    • Meeting date: 08 December 2004
    How many emergency services staff will be available at short notice to respond to a major incident, including from the armed services? How many of these will have been trained to respond to a CBRN incident, and is it compulsory for emergency services staff to respond to a CBRN incident?