Asked of 3

  • Lead off question - Delays to Crossrail (Supplementary) [3]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you for that. Will the decision to delay the opening until autumn next year [2019] ‑ it would be great to find out which month in autumn ‑ mean further delay in the opening of the other sections and the final full opening of the line in December 2019?
  • Lead off question - Delays to Crossrail (Supplementary) [7]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Simon, is there anything you want to add to that?
  • Lead off question - Delays to Crossrail (Supplementary) [13]

    • Question by: David Kurten
    • Meeting date: 06 September 2018
    David Kurten AM: Let us come back to the technical aspects. It seems the main problems are getting the three different signalling infrastructures to talk to each other. If you had an extension from Abbey Wood to Ebbsfleet then you would need Crossrail to go onto Southeastern track, which might be a fourth signalling structure. Would it not be? You are shaking your heads.
  • Flooding Action Plan

    • Reference: 2015/3751
    • Question by: Steve O'Connell
    • Meeting date: 18 November 2015
    What changes do you anticipate to the London Plan or other planning guidance as a result of your new action plan to help tackle flooding risks in London?
  • Starter Homes

    • Reference: 2015/3301
    • Question by: Steve O'Connell
    • Meeting date: 21 October 2015
    How will you be taking forward the Government's recent announcement to enable the delivery of Starter Homes in London?
  • Sutton Transport Improvements

    • Reference: 2015/0402
    • Question by: Steve O'Connell
    • Meeting date: 21 January 2015
    In December you visited The Institute of Cancer Research in Belmont, where you made clear that you strongly supported the plans to expand to become the second biggest campus of its kind in the world. What effect will these plans have on the business case for the Sutton Tram Extension?
  • Temporary Venues

    • Reference: 2009/0122-1
    • Question by: Andrew Boff
    • Meeting date: 21 October 2009
    To what extent have LOCOG been successful in ensuring value for money and adequate public consultation in relation to temporary venues?
  • Temporary Venues (Supplementary) [1]

    • Question by: Gareth Bacon MP
    • Meeting date: 21 October 2009
    I am going to focus in on Greenwich, which, I am sure you are both aware, is becoming a slightly controversial area. A quick opening question: in the bid book the estimated cost for the temporary venues in Greenwich Park was £8.8 million. What is the current estimated cost?
  • Legacy Master plan for the Olympic Park (Supplementary) [1]

    • Question by: Dee Doocey
    • Meeting date: 10 November 2007
    And what is the answer to my question? Why did nobody provide coaches, buses or train tickets and depend on the parents driving 300-mile round trips every weekend?
  • Legacy Master plan for the Olympic Park (Supplementary) [3]

    • Question by: Dee Doocey
    • Meeting date: 10 November 2007
    My final question is to Seb. Seb, does it worry you, as I am sure it should, that we keep reading things in the press about divers having to go to Sheffield and cyclists having to drive round the M25 in rush hour during the week in order to be able to train? Nobody could have foreseen that there were going to be problems with Crystal Palace? Surely these are the people that you are trying to inspire; these are the people that you are reaching out to so successfully. Once you realised that these people had to go to...