  • Jack Lemley

    • Reference: 2006/0389-1
    • Question by: Brian Coleman
    • Meeting date: 15 November 2006
    In his remarks to the Idaho Statesman, Jack Lemley said that political disputes will make the Olympics come in late and over budget. Is he telling the truth, or is he deliberately trying to mislead?
  • Budget

    • Reference: 2006/0391-1
    • Question by: Brian Coleman
    • Meeting date: 15 November 2006
    Mr Lemley was also concerned about soaring costs. Given that you are going to the Treasury to ask for extra money for the regeneration that was promised, why was the Olympic Delivery Authority not upfront about the real cost of the promised legacy from the outset?
  • Delays to the Project:

    • Reference: 2006/0392-1
    • Question by: Brian Coleman
    • Meeting date: 15 November 2006
    Mr Lemley also predicted that, despite your assurances, Games venues will not be delivered on schedule. Please can you confirm the date on which construction work on the stadium, the aquatic centre and the Olympic village will be completed?
  • Green Grid

    • Reference: 2006/0132-1
    • Question by: Jenny Jones
    • Meeting date: 11 October 2006
    Where does the Green Grid fit within the LDA's future priorities for East London?
  • Olympics

    • Reference: 2006/0141-1
    • Question by: Bob Blackman
    • Meeting date: 11 October 2006
    What problems or delays have there been in the land assembly for the Olympics and the first project of laying the power lines?
  • Future Staffing

    • Reference: 2006/0142-1
    • Question by: Angie Bray
    • Meeting date: 11 October 2006
    What assessment has been made of the future staffing needs of the LDA as a result of the review of powers and where will these people be assigned?
  • Olympics Role

    • Reference: 2006/0207-1
    • Question by: John Biggs
    • Meeting date: 11 October 2006
    How is the LDA Olympic role changing with the creation and transfer of responsibilities to the ODA?
  • Crystal Palace Park

    • Reference: 2006/0211-1
    • Question by: Valerie Shawcross
    • Meeting date: 11 October 2006
    The decision by Sport England not to fund the replacement of the Sports centre, and the block placed by English Partnerships on demolishing the existing Sports Centre has had a profound effect on the phasing and outcomes of this project - will you restate your proposals in summary for the public record and re-iterate your commitment to restoring and regenerating the park?
  • Barriers to Employment

    • Reference: 2006/0219-1
    • Question by: Murad Qureshi
    • Meeting date: 11 October 2006
    With 30% of working age Londoners workless how will the LDA meet the challenge of tackling barriers to employment?
  • Caribbean Showcase Sponsorship

    • Reference: 2006/0226-1
    • Question by: Damian Hockney
    • Meeting date: 11 October 2006
    What criteria were used when the LDA decided to sponsor the Mayor's Caribbean Showcase event at a cost to the taxpayer of £215,000 (£120,000 directly and £95,000 through its offshoot "Creative London")?