  • Lead off question - Delays to Crossrail (Supplementary) [3]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you for that. Will the decision to delay the opening until autumn next year [2019] ‑ it would be great to find out which month in autumn ‑ mean further delay in the opening of the other sections and the final full opening of the line in December 2019?
  • Lead off question - Delays to Crossrail (Supplementary) [7]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Simon, is there anything you want to add to that?
  • Lead off question - Delays to Crossrail (Supplementary) [13]

    • Question by: David Kurten
    • Meeting date: 06 September 2018
    David Kurten AM: Let us come back to the technical aspects. It seems the main problems are getting the three different signalling infrastructures to talk to each other. If you had an extension from Abbey Wood to Ebbsfleet then you would need Crossrail to go onto Southeastern track, which might be a fourth signalling structure. Would it not be? You are shaking your heads.
  • Update since September 2017 plenary

    • Reference: 2018/1693
    • Question by: Navin Shah
    • Meeting date: 05 July 2018
    Please could you provide an update of the OPDC’s work since you last met the Assembly in September 2017?
  • Tenure split of 'affordable homes' in the Old Oak and Park Royal Development Corporation area

    • Reference: 2018/1695
    • Question by: Siân Berry
    • Meeting date: 05 July 2018
    Could you provide an update on the numbers of 'affordable homes' of each tenure that you expect to deliver in the OPDC area?
  • Maximising the OPDC’s benefit to London

    • Reference: 2018/1696
    • Question by: Lord Bailey of Paddington
    • Meeting date: 05 July 2018
    How much money would the OPDC need to enable it to maximise its potential benefit to London?
  • New London Overground Stations

    • Reference: 2018/1694
    • Question by: Florence Eshalomi MP
    • Meeting date: 05 July 2018
    In order to fund two new London Overground Stations what support will be offered by developers and businesses in the opportunity area?
  • Update since September 2017 plenary (Supplementary) [1]

    • Question by: Caroline Pidgeon
    • Meeting date: 05 July 2018
    Caroline Pidgeon MBE AM: Since we last met, the Office for National Statistics (ONS) has said that 28% of London’s construction workers are from the European Union (EU). In light of this and given that the Deputy Mayor for Housing [and Residential Development] has said an additional 13,000 construction workers are needed in the capital, perhaps, Liz, as Chairman, you could advise me, do you think there are going to be problems in getting your project built?
  • Update since September 2017 plenary (Supplementary) [2]

    • Question by: Leonie Cooper
    • Meeting date: 05 July 2018
    Leonie Cooper AM: Thank you very much, Chairman. My question is about the leadership, which I have asked about before. Does the OPDC have the right leadership in place to meet the challenges of the next five years?
  • Update since September 2017 plenary (Supplementary) [3]

    • Question by: Unmesh Desai
    • Meeting date: 05 July 2018
    Unmesh Desai AM: Can I ask you how you intend to go about attracting the necessary finance that you need to realise your ambitions for the regeneration of Old Oak? In particular, what concerns me is how you will address any associated financial risk?