    Shaun Bailey AM: Thank you, Chair. Good morning, all. Can I address my first question to Deputy Mayor Agrawal, please? When restrictions are easing and are being pulled back, what work is being done to prepare London to reopen, by the Mayor’s Office and by your office as well, please?
  • Effectiveness of the LEAP

    • Reference: 2019/11381
    • Question by: Susan Hall
    • Meeting date: 06 June 2019
    How would you rate the effectiveness of the LEAP?
  • Supporting Economic Growth

    • Reference: 2019/11382
    • Question by: Leonie Cooper
    • Meeting date: 06 June 2019
    Since the LEAP was created, what actions have you taken to support economic growth and job creation in the capital?
  • Underspends in community and environmental projects

    • Reference: 2019/11380
    • Question by: Caroline Russell
    • Meeting date: 06 June 2019
    Could you explain why there are significant underspends in your support for community and environmental projects?
  • Lead off question - Delays to Crossrail (Supplementary) [3]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you for that. Will the decision to delay the opening until autumn next year [2019] ‑ it would be great to find out which month in autumn ‑ mean further delay in the opening of the other sections and the final full opening of the line in December 2019?
  • Lead off question - Delays to Crossrail (Supplementary) [7]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Simon, is there anything you want to add to that?
  • Lead off question - Delays to Crossrail (Supplementary) [13]

    • Question by: David Kurten
    • Meeting date: 06 September 2018
    David Kurten AM: Let us come back to the technical aspects. It seems the main problems are getting the three different signalling infrastructures to talk to each other. If you had an extension from Abbey Wood to Ebbsfleet then you would need Crossrail to go onto Southeastern track, which might be a fourth signalling structure. Would it not be? You are shaking your heads.
  • Update since September 2017 plenary

    • Reference: 2018/1693
    • Question by: Navin Shah
    • Meeting date: 05 July 2018
    Please could you provide an update of the OPDC’s work since you last met the Assembly in September 2017?
  • Tenure split of 'affordable homes' in the Old Oak and Park Royal Development Corporation area

    • Reference: 2018/1695
    • Question by: Siân Berry
    • Meeting date: 05 July 2018
    Could you provide an update on the numbers of 'affordable homes' of each tenure that you expect to deliver in the OPDC area?
  • Maximising the OPDC’s benefit to London

    • Reference: 2018/1696
    • Question by: Lord Bailey of Paddington
    • Meeting date: 05 July 2018
    How much money would the OPDC need to enable it to maximise its potential benefit to London?