  • Lead off question - Delays to Crossrail (Supplementary) [2]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Mr Mayor, on 25 July there was an item on Crossrail in the private section of the TfL Board, which you chair, as well as the public section. Were any concerns raised? As Simon has outlined, the programme is building up and you are getting concerned. Were any concerns raised there about the possibility of delay in the opening?
  • Lead off question - Delays to Crossrail (Supplementary) [3]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you for that. Will the decision to delay the opening until autumn next year [2019] ‑ it would be great to find out which month in autumn ‑ mean further delay in the opening of the other sections and the final full opening of the line in December 2019?
  • Lead off question - Delays to Crossrail (Supplementary) [4]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Finally, time is money in the construction sector. There will inevitably be an additional cost with this delay. Who is going to be picking up that bill, is it TfL and Londoners or is it going to be the DfT?
  • Lead off question - Delays to Crossrail (Supplementary) [5]

    • Question by: Gareth Bacon MP
    • Meeting date: 06 September 2018
    Gareth Bacon AM: This is to the Commissioner, Mr Brown. What are the financial implications of this?
  • Lead off question - Delays to Crossrail (Supplementary) [7]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Simon, is there anything you want to add to that?
  • Lead off question - Delays to Crossrail (Supplementary) [8]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Mike, obviously there are still major ambitions in TfL’s finances and the TfL budget in terms of Crossrail 2. TfL has said it will be able to pay for half of Crossrail 2. Do you think this would still be the case, given we are seeing a delay in Crossrail 1?
  • Lead off question - Delays to Crossrail (Supplementary) [11]

    • Question by: Caroline Russell
    • Meeting date: 06 September 2018
    Caroline Russell AM: OK. I am going to ask Mike now. The status quo on Oxford Street is not OK. We know that urgent attention is needed to deal even with the current overcrowding, let alone with the overcrowding that will come from the new Crossrail passengers. Has TfL done a Healthy Streets check on Oxford Street in its current condition, and if not, will you?
  • Lead off question - Delays to Crossrail (Supplementary) [13]

    • Question by: David Kurten
    • Meeting date: 06 September 2018
    David Kurten AM: Let us come back to the technical aspects. It seems the main problems are getting the three different signalling infrastructures to talk to each other. If you had an extension from Abbey Wood to Ebbsfleet then you would need Crossrail to go onto Southeastern track, which might be a fourth signalling structure. Would it not be? You are shaking your heads.