Asked of 2

  • Lead off question - Delays to Crossrail (Supplementary) [2]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Mr Mayor, on 25 July there was an item on Crossrail in the private section of the TfL Board, which you chair, as well as the public section. Were any concerns raised? As Simon has outlined, the programme is building up and you are getting concerned. Were any concerns raised there about the possibility of delay in the opening?
  • Lead off question - Delays to Crossrail (Supplementary) [4]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Finally, time is money in the construction sector. There will inevitably be an additional cost with this delay. Who is going to be picking up that bill, is it TfL and Londoners or is it going to be the DfT?
  • Jack Lemley (Supplementary) [1]

    • Question by: Dee Doocey
    • Meeting date: 15 November 2006
    Thank you. My last question is about the budget. I understand that the budget has not been finalised, but you should surely realise that the reason we have so much concern around here is because we have not got any information. The job we are being paid to do is to monitor the delivery of the Games. We cannot actually monitor it if we do not have the budget, because we do not know whether you are going above it or below it. Now you have said that the budget that you have asked for is significantly higher than the...
  • Jack Lemley (Supplementary) [2]

    • Question by: Dee Doocey
    • Meeting date: 15 November 2006
    I would like to know what plans are in place to make sure that the same mistakes do not happen again when there is a new Chairman appointed. I think it is very clear, certainly to me, that Mr Lemley has done much more damage to his own reputation by his extraordinary behaviour since he left, than could ever have been done by the involvement with the Games. I wanted to know how it was going to be made sure that whoever is appointed next time, and whoever is going to appoint them - presumably the Mayor and the Secretary...
  • Budget (Supplementary) [11]

    • Question by: Sally Hamwee
    • Meeting date: 15 November 2006
    A discrete point, as it were. You have mentioned the need for an adequate contingency budget. I do not think any one would argue with that. Are you able to tell us, in terms of the percentage of the whole, what you would regard as an adequate percentage?
  • Environment

    • Reference: 2006/0109-1
    • Question by: Mike Tuffrey
    • Meeting date: 14 June 2006
    What estimate have you made of the amount of carbon that will be produced in the construction of the Olympic Park?