  • London Recovery Board and London Transition Board (Supplementary) [14]

    • Question by: Alison Moore
    • Meeting date: 02 July 2020
    Dr Alison Moore AM: Thank you very much, Chair. My question is for Niran Mothada. London’s transport system is critical to the functioning of the city, as we all know. How will your Board marry up the impact that COVID-19 is having on transport, both its finances and how Londoners will move about in the future, with individual and business needs so that London remains open?
  • London Recovery Board and London Transition Board (Supplementary) [15]

    • Question by: Navin Shah
    • Meeting date: 02 July 2020
    Navin Shah AM: Thank you very much. My question is on mental health and the question is to Niran Mothada. The mental health of Londoners has been hugely impacted by COVID-19. What are the arrangements made for supporting Londoners with mental health issues arising out of the pandemic and how is it going to be dealt with in the new normality in the capital?
  • London Recovery Board and London Transition Board (Supplementary) [16]

    • Question by: Murad Qureshi
    • Meeting date: 02 July 2020
    Murad Qureshi AM: Thank you, Chair. My question on childcare is addressed to Niran Mothada, the Executive Director of Strategy and Communications. Childcare is going to be a huge issue when Londoners return to work and in fact has actually been a huge issue whilst we have been in lockdown, as women have been taking up the bulk of caring duties. How can the Board support parents returning to work either at the office or from home, given that I understand 34% of early years providers are facing closure due to COVID-19, as reported by the Sutton Trust?
  • London Recovery Board and London Transition Board (Supplementary) [17]

    • Question by: Joanne McCartney
    • Meeting date: 02 July 2020
    Joanne McCartney AM: My question is to Niran. Looking forward at economic recovery, do you think there is a balance between jobs, in terms of the amount of jobs and job security we can offer, and making sure that companies offer good terms and conditions? Is that something that the Recovery Board has at the forefront of its mind?
  • London Recovery Board and London Transition Board (Supplementary) [18]

    • Question by: Nicky Gavron
    • Meeting date: 02 July 2020
    Nicky Gavron AM: Thank you very much, Chair. I want to add my thanks to the team and the panel in front of us for all the work you are doing. My question is to Niran Mothada. To ensure that we have a real green economic recovery and a just transition, will you be building into the social recovery working group and the economic recovery working group green thinking at the very heart of all the work that it has been doing and is going to do? Also, can you tell me how you are going to translate the principles...
  • Lead off question - Delays to Crossrail (Supplementary) [1]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you. Mr Mayor, just ten weeks ago, in answer to a Mayoral question (MQ), you stated, “The Elizabeth line remains on course to open as planned in December 2018”. The Commissioner, in the TfL Board report of 25 July [2018] stated, “Crossrail remains on course to open as planned in December”. Sir Terry, on 6 June, when the Transport Committee visited Tottenham Court Road with you, you gave me an absolute assurance that the opening of Crossrail would be in December. You even confirmed the date, Sunday, 9 December when the Queen would be opening...
  • Lead off question - Delays to Crossrail (Supplementary) [6]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Thank you. To come back to Crossrail, on this side [of the table] we definitely recognise the scale of this project but once completed it will be a big success for London. I am definitely looking forward to when it opens. You may be aware of Rob Holden’s [CBE, Chairman, High Speed 1] letter last week in The Times where he stated, “The problems with Crossrail arose from the decision taken in 2011 to delay the procurement of new rolling stock, a decision that has affected the commissioning of those new trains ... signalling was always going...
  • Lead off question - Delays to Crossrail (Supplementary) [9]

    • Question by: Caroline Russell
    • Meeting date: 06 September 2018
    Caroline Russell AM: Thank you, Chairman. I want to ask about the experience of the passengers who are waiting to use this line but before I get on to those questions I want to pick up on something that Sir Terry said at the very beginning. You said, “We mitigated one risk and others materialised”. I wonder if you could expand on that a bit more, whether that is what has caused this decision about the delay.
  • Lead off question - Delays to Crossrail (Supplementary) [14]

    • Question by: Keith Prince
    • Meeting date: 06 September 2018
    Keith Prince AM: Thank you, Chairman. Good morning, Sir Terry. I am trying to get some dates straight in my head. You mentioned a Board meeting in July [2018] where it was raised that there could be problems. Could you tell me the date of that meeting in July, please?