Asked of 1

  • Jack Lemley (Supplementary) [1]

    • Question by: Dee Doocey
    • Meeting date: 15 November 2006
    Thank you. My last question is about the budget. I understand that the budget has not been finalised, but you should surely realise that the reason we have so much concern around here is because we have not got any information. The job we are being paid to do is to monitor the delivery of the Games. We cannot actually monitor it if we do not have the budget, because we do not know whether you are going above it or below it. Now you have said that the budget that you have asked for is significantly higher than the...
  • Jack Lemley (Supplementary) [2]

    • Question by: Dee Doocey
    • Meeting date: 15 November 2006
    I would like to know what plans are in place to make sure that the same mistakes do not happen again when there is a new Chairman appointed. I think it is very clear, certainly to me, that Mr Lemley has done much more damage to his own reputation by his extraordinary behaviour since he left, than could ever have been done by the involvement with the Games. I wanted to know how it was going to be made sure that whoever is appointed next time, and whoever is going to appoint them - presumably the Mayor and the Secretary...
  • Budget (Supplementary) [7]

    • Question by: Darren Johnson
    • Meeting date: 15 November 2006
    But you cannot give a guarantee?
  • Budget (Supplementary) [12]

    • Question by: Darren Johnson
    • Meeting date: 15 November 2006
    Okay, so the environment is a major feature, but we may have to see some scaling down on the bid commitments because of cost overruns?
  • Budget (Supplementary) [16]

    • Question by: Darren Johnson
    • Meeting date: 15 November 2006
    On the budget issue, we saw environmental and legacy commitments being scaled back in Athens as a result of going over budget. Can you give an absolute guarantee that there will be no scaling back in London from what was promised in the bid documents?
  • Renewable Energy

    • Reference: 2006/0104-1
    • Question by: Darren Johnson
    • Meeting date: 14 June 2006
    Existing planning permission for the Stratford City development specifies that a minimum of 2% of energy requirements of the development be provided from locally resourced renewable energy. This is a long way short of the commitment in Towards a One Planet Olympics for an 'Athletes' Village capable of being energy self-sufficient'. As part of the Athletes' Village will now be sited within the Stratford City development, will the ODA seek new planning permission, specifying the Athletes' Village as a Zero-Energy Development? If not, how will the ODA ensure that the Athletes' Village is "energy self -sufficient"?