  • Lead off question - Delays to Crossrail (Supplementary) [1]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you. Mr Mayor, just ten weeks ago, in answer to a Mayoral question (MQ), you stated, “The Elizabeth line remains on course to open as planned in December 2018”. The Commissioner, in the TfL Board report of 25 July [2018] stated, “Crossrail remains on course to open as planned in December”. Sir Terry, on 6 June, when the Transport Committee visited Tottenham Court Road with you, you gave me an absolute assurance that the opening of Crossrail would be in December. You even confirmed the date, Sunday, 9 December when the Queen would be opening...
  • Lead off question - Delays to Crossrail (Supplementary) [6]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Thank you. To come back to Crossrail, on this side [of the table] we definitely recognise the scale of this project but once completed it will be a big success for London. I am definitely looking forward to when it opens. You may be aware of Rob Holden’s [CBE, Chairman, High Speed 1] letter last week in The Times where he stated, “The problems with Crossrail arose from the decision taken in 2011 to delay the procurement of new rolling stock, a decision that has affected the commissioning of those new trains ... signalling was always going...