  • Bonuses

    • Reference: 2007/2312
    • Question by: Sally Hamwee
    • Meeting date: 17 October 2007
    Please provide me with the number of employees awarded performance bonuses, and the value of these bonuses by the LDA and TfL, in the last financial year, and the total paid out by each organisation.
  • Retrospective agreement MA3036

    • Reference: 2007/2313
    • Question by: Sally Hamwee
    • Meeting date: 17 October 2007
    The retrospective agreement to an extension of the finance system contract took place nearly a year after the extension was awarded. Can you explain the reason for this delay? Do you consider agreeing to contracts 10 months after they are awarded good practice?
  • MA3186 Black History Month

    • Reference: 2007/2314
    • Question by: Sally Hamwee
    • Meeting date: 17 October 2007
    Could you provide a break down of the functional body income referred to in MA3186 by functional body?
  • Procurement of IT services

    • Reference: 2007/2315
    • Question by: Sally Hamwee
    • Meeting date: 17 October 2007
    Why is the GLA procuring the services of Yahya Saeed (DA1820) in accordance with the TfL Agency Suppliers Framework rather than using GLA processes?
  • Vacancy Rate

    • Reference: 2007/2322
    • Question by: Sally Hamwee
    • Meeting date: 17 October 2007
    Can you confirm your answer to question 1971/2007 that at that point (September 2007) the GLA's vacancy rate was 12%? Considering the vacancy rate over 2006/07 was only 4.5% what is the reason for this very high snapshot rate?
  • Beckton desalination plant appeal

    • Reference: 2007/2323
    • Question by: Sally Hamwee
    • Meeting date: 17 October 2007
    Considering the difficulty of predicting the final costs of your appeal against the planning permission given to the Beckton desalination plant, what contingency is being made to cover any costs that do arise?
  • Agency Staff (1)

    • Reference: 2007/1966
    • Question by: Sally Hamwee
    • Meeting date: 12 September 2007
    What was the total spend on temporary staff recruited through agencies in 2006/07 by the core GLA?
  • Agency Staff (2)

    • Reference: 2007/1967
    • Question by: Sally Hamwee
    • Meeting date: 12 September 2007
    In 2006/07, through how many agencies did the GLA find temporary staff? With how many of these agencies did the GLA have a contract?
  • Sponsorship Team

    • Reference: 2007/1969
    • Question by: Sally Hamwee
    • Meeting date: 12 September 2007
    What was the total raised by the GLA sponsorship team in 2006/07 and what was the gross cost of the team in the same year, broken down into pay and non-pay costs?
  • Vacancy Rate (1)

    • Reference: 2007/1970
    • Question by: Sally Hamwee
    • Meeting date: 12 September 2007
    What was the vacancy rate in the core GLA in 2006/07?