- Reference: 2018/1201
- Question by: Nicky Gavron
- Meeting date: 17 May 2018
Your Stage 1 report (https://www.london.gov.uk/sites/default/files/dp3109astg1.pdf) on the Newcombe House Planning application says, "The applicant has been involved in discussions with London Underground on the previous application and terms had been agreed for the s106 as well as the associated arrangements for the delivery of the works. The cost of providing the space, the required structure and fitting out of the step-free access is estimated at £5.2M and should be delivered by the developer." Is this £5.2m cost still accurate and will London Underground be required to provide funding to make the eastbound platform of the station step free?