Skip to main content
Mayor of London logo London Assembly logo
Home

Search questions

Filter results

Asked of 2

  • Lead off question - Delays to Crossrail (Supplementary) [2]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Mr Mayor, on 25 July there was an item on Crossrail in the private section of the TfL Board, which you chair, as well as the public section. Were any concerns raised? As Simon has outlined, the programme is building up and you are getting concerned. Were any concerns raised there about the possibility of delay in the opening?
  • Lead off question - Delays to Crossrail (Supplementary) [4]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Finally, time is money in the construction sector. There will inevitably be an additional cost with this delay. Who is going to be picking up that bill, is it TfL and Londoners or is it going to be the DfT?
  • Lead off question - Delays to Crossrail (Supplementary) [5]

    • Question by: Gareth Bacon MP
    • Meeting date: 06 September 2018
    Gareth Bacon AM: This is to the Commissioner, Mr Brown. What are the financial implications of this?
  • Lead off question - Delays to Crossrail (Supplementary) [8]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Mike, obviously there are still major ambitions in TfL’s finances and the TfL budget in terms of Crossrail 2. TfL has said it will be able to pay for half of Crossrail 2. Do you think this would still be the case, given we are seeing a delay in Crossrail 1?
  • Lead off question - Delays to Crossrail (Supplementary) [11]

    • Question by: Caroline Russell
    • Meeting date: 06 September 2018
    Caroline Russell AM: OK. I am going to ask Mike now. The status quo on Oxford Street is not OK. We know that urgent attention is needed to deal even with the current overcrowding, let alone with the overcrowding that will come from the new Crossrail passengers. Has TfL done a Healthy Streets check on Oxford Street in its current condition, and if not, will you?
  • Transport

    • Reference: 2003/0308
    • Question by: Roger Evans
    • Meeting date: 15 October 2003
    What transport demand modelling is currently being undertaken to establish the volume of passenger demand and the predicted transport patterns? If this modelling is being undertaken, who is carrying this work out? If it is not happening, why not? .
  • Transport

    • Reference: 2003/0309
    • Question by: John Biggs
    • Meeting date: 15 October 2003
    How do you see existing transport links servicing an Olympics based at Stratford? Would there be any need for new routes, access or other transport infrastructure and if so, what? .
  • Transport (Supplementary) [4]

    • Question by: John Biggs
    • Meeting date: 15 October 2003
  • Transport (Supplementary) [6]

    • Question by: Nicky Gavron
    • Meeting date: 15 October 2003
    Doubling the track?
  • Transport (Supplementary) [7]

    • Question by: Nicky Gavron
    • Meeting date: 15 October 2003
    I agree that we have to get the existing transport infrastructure right. There is a direct link from Stratford to Stansted which is growing very fast in the period up to the Games. It cannot be used. It needs two things. Firstly, the doubling of the track capacity between Tottenham Hale and Broxbourne, which was planned for completion by 2007 but is now being consigned to the distant future by the SRA. It was one of their top priorities, but now it is out. Secondly, improvements are needed to the Copper Mill junction on the link between Tottenham Hale and...