  • Lead off question - Delays to Crossrail (Supplementary) [1]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you. Mr Mayor, just ten weeks ago, in answer to a Mayoral question (MQ), you stated, “The Elizabeth line remains on course to open as planned in December 2018”. The Commissioner, in the TfL Board report of 25 July [2018] stated, “Crossrail remains on course to open as planned in December”. Sir Terry, on 6 June, when the Transport Committee visited Tottenham Court Road with you, you gave me an absolute assurance that the opening of Crossrail would be in December. You even confirmed the date, Sunday, 9 December when the Queen would be opening...
  • Lead off question - Delays to Crossrail (Supplementary) [6]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Thank you. To come back to Crossrail, on this side [of the table] we definitely recognise the scale of this project but once completed it will be a big success for London. I am definitely looking forward to when it opens. You may be aware of Rob Holden’s [CBE, Chairman, High Speed 1] letter last week in The Times where he stated, “The problems with Crossrail arose from the decision taken in 2011 to delay the procurement of new rolling stock, a decision that has affected the commissioning of those new trains ... signalling was always going...
  • Lead off question - Delays to Crossrail (Supplementary) [9]

    • Question by: Caroline Russell
    • Meeting date: 06 September 2018
    Caroline Russell AM: Thank you, Chairman. I want to ask about the experience of the passengers who are waiting to use this line but before I get on to those questions I want to pick up on something that Sir Terry said at the very beginning. You said, “We mitigated one risk and others materialised”. I wonder if you could expand on that a bit more, whether that is what has caused this decision about the delay.
  • Lead off question - Delays to Crossrail (Supplementary) [14]

    • Question by: Keith Prince
    • Meeting date: 06 September 2018
    Keith Prince AM: Thank you, Chairman. Good morning, Sir Terry. I am trying to get some dates straight in my head. You mentioned a Board meeting in July [2018] where it was raised that there could be problems. Could you tell me the date of that meeting in July, please?
  • Infrastructure recovery (Supplementary) [8]

    • Question by: Brian Coleman
    • Meeting date: 08 December 2004
    I vaguely think that is a 'yes,' but never mind.
  • Evacuation and care of Schoolchildren (Supplementary) [1]

    • Question by: Elizabeth Howlett
    • Meeting date: 08 December 2004
    Thank you very much. One is still a little bit worried. I do not think I have had a proper answer, but my concerns are really about the legal responsibilities that local authorities ' the educational authorities ' may have. One presumes that in a critical incident, children may be removed to a separate, secure place from their parents. Now, this raises the question about legal and practical care to ensure that the children are well-cared for in the short- and medium-term. Now, the term 'in loco parentis' is, in fact, common law, and it does not assume the responsibility...
  • Fresh Food Supply

    • Reference: 2004/0390-1
    • Question by: Jenny Jones
    • Meeting date: 08 December 2004
    What is being done to ensure that in the event of a major crisis there will be an adequate supply of fresh food for Londoners?