  • Lead off question - Delays to Crossrail (Supplementary) [3]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you for that. Will the decision to delay the opening until autumn next year [2019] ‑ it would be great to find out which month in autumn ‑ mean further delay in the opening of the other sections and the final full opening of the line in December 2019?
  • Lead off question - Delays to Crossrail (Supplementary) [7]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Simon, is there anything you want to add to that?
  • Lead off question - Delays to Crossrail (Supplementary) [13]

    • Question by: David Kurten
    • Meeting date: 06 September 2018
    David Kurten AM: Let us come back to the technical aspects. It seems the main problems are getting the three different signalling infrastructures to talk to each other. If you had an extension from Abbey Wood to Ebbsfleet then you would need Crossrail to go onto Southeastern track, which might be a fourth signalling structure. Would it not be? You are shaking your heads.
  • Net addition to social housing stock

    • Reference: 2015/1668
    • Question by: Darren Johnson
    • Meeting date: 17 June 2015
    What net addition to the social housing stock in London should you be making each year?
  • Transport for London Business Plan (Supplementary) [2]

    • Question by: John Biggs
    • Meeting date: 23 May 2012
    Darren Johnson (Deputy Chair): Assembly Member Biggs has a point of order. John Biggs (AM): The Chair told us there was a standing order about making assertions for which there was no evidence. Now, the Mayor has at the one time made an assertion for which he has evidence that he can cut council tax. Now he has made another assertion that on fares, he can make no such commitment. There is a fundamental inconsistency, it seems to me, under standing orders. Either one can be said and the other cannot, and either the both can be said or neither...
  • Congestion Charge - Additional Costs to Businesses (Supplementary) [6]

    • Question by: Damian Hockney
    • Meeting date: 06 December 2006
    Do you ask this question though; are your delivery companies and so on charging you?
  • Public Announcement Noise at Tube Stations (Supplementary) [4]

    • Question by: Murad Qureshi
    • Meeting date: 18 November 2006
    I do often go through Earl's Court, simply because I can never get a Circle Line Tube, so I have to go there to get onto a District Line to go down in that part of West London. Should the emphasis not actually be on electronic information and the signs there being replaced as quickly as possible with electronic information, rather than putting it out on a tannoy, which I actually have not heard ever whenever I pass right through Earl's Court?