  • Lead off question - Delays to Crossrail (Supplementary) [3]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you for that. Will the decision to delay the opening until autumn next year [2019] ‑ it would be great to find out which month in autumn ‑ mean further delay in the opening of the other sections and the final full opening of the line in December 2019?
  • Lead off question - Delays to Crossrail (Supplementary) [7]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Simon, is there anything you want to add to that?
  • Lead off question - Delays to Crossrail (Supplementary) [13]

    • Question by: David Kurten
    • Meeting date: 06 September 2018
    David Kurten AM: Let us come back to the technical aspects. It seems the main problems are getting the three different signalling infrastructures to talk to each other. If you had an extension from Abbey Wood to Ebbsfleet then you would need Crossrail to go onto Southeastern track, which might be a fourth signalling structure. Would it not be? You are shaking your heads.
  • Priorities for the OPDC (Supplementary) [3]

    • Question by: Tom Copley
    • Meeting date: 08 March 2017
    Tom Copley AM: My next question perhaps is more for David [Bellamy] or Fiona. The report from the review recommends that public land is potentially wholly transferred to the GLA. To what extent does central Government recognise the complexities of the land and what discussions had the Mayor had around the proposal of land transfer?