Asked of 3

  • Lead off question - Delays to Crossrail (Supplementary) [3]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you for that. Will the decision to delay the opening until autumn next year [2019] ‑ it would be great to find out which month in autumn ‑ mean further delay in the opening of the other sections and the final full opening of the line in December 2019?
  • Lead off question - Delays to Crossrail (Supplementary) [7]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Simon, is there anything you want to add to that?
  • Lead off question - Delays to Crossrail (Supplementary) [13]

    • Question by: David Kurten
    • Meeting date: 06 September 2018
    David Kurten AM: Let us come back to the technical aspects. It seems the main problems are getting the three different signalling infrastructures to talk to each other. If you had an extension from Abbey Wood to Ebbsfleet then you would need Crossrail to go onto Southeastern track, which might be a fourth signalling structure. Would it not be? You are shaking your heads.
  • Tackling Homelessness in London

    • Reference: 2018/0231
    • Question by: Tom Copley
    • Meeting date: 18 January 2018
    How will the Mayor's 'No one needs to sleep rough in London' campaign and new London Homeless Charities Group contribute to reducing homelessness in the capital?
  • Vision for Old Oak Common (Supplementary) [5]

    • Question by: Tom Copley
    • Meeting date: 07 September 2017
    Tom Copley AM: Thank you very much, Chair. I wanted to ask you about the levels of affordable housing and specifically the London Affordable [Living] Rent which is the Mayor’s new form of tenure that is going to be benchmarked at social rent levels. Are you going to have a target specifically for London Affordable Rent across the OPDC site?
  • Local Government Asset Sales

    • Reference: 2015/2220
    • Question by: Tom Copley
    • Meeting date: 15 July 2015
    Given the Government's proposals to force London's local authorities to sell high value assets, do you think the revenue generated should be hypothecated for building homes in the capital?
  • Housing supply

    • Reference: 2015/0112
    • Question by: Tom Copley
    • Meeting date: 21 January 2015
    In your Housing Strategy you outline that you "would like to see new arrangements for prudential borrowing for new housing so that it is not counted as Government debt, which would distinguish it from more mainstream public borrowing, along the lines that apply in much of the rest of Europe". What progress have you made in lobbying the government to implement this change?
  • Evacuation plans (Supplementary) [8]

    • Question by: Mike Tuffrey
    • Meeting date: 08 December 2004
    Thinking about evacuation, I am sure you will agree it is important that the extent to which people are educated in advance of the crisis about what is expected of them will help in the management at the time. Looking at the Preparing for Emergencies booklet, which has been mentioned, that has three generic bullet points on this issue, and if you compare that with what is available to New Yorkers, in terms of a very detailed guide, with evacuation there absolutely, all sorts of things, down to what to do with your pets, which I am sure is a...
  • Infrastructure recovery (Supplementary) [1]

    • Question by: Bob Neill
    • Meeting date: 08 December 2004
    Bob Neill (AM): I am sure that is right. It is a shame that GOL are not here so that we could have heard it be said. Brian Coleman (Chair): Indeed, we wish Mr Kowalczyk was here, so we could pay tribute to him this morning, but unfortunately he is not. I am sure, however, his spies are in the audience somewhere. Can I just ask, Mr Mayer, are you saying we need, in your professional opinion as an officer ' or 'mere bureaucrat,' as you describe yourself ' that we need an office of emergency planning in London?
  • Infrastructure recovery (Supplementary) [2]

    • Question by: Graham Tope
    • Meeting date: 08 December 2004
    Let me share your optimism and your confidence ' which I think I do, really ' for what would happen in, say, the first 48 hours, when we deal with the immediate crisis. What I would like to probe is what happens after the first, say, 48 hours, when we really are getting into the recovery period, when it is, perhaps, less of a crisis and more of an emergency. Who is going to be taking charge then? What is the role of the Mayor and the GLA, and what are the roles of the individual London boroughs? Who is...