Skip to main content
Mayor of London logo London Assembly logo
Home

Search questions

Filter results

Asked of 2

  • Question and Answer Session: Olympic Park Legacy Company (Supplementary) [3]

    • Question by: Jennette Arnold OBE
    • Meeting date: 16 March 2011
    Thank you, Chair. I have got a number of questions. Firstly, to go back to what John was talking about, on the people legacy. The Olympic Park set itself benchmarks, as you know, Margaret. I know that you have been aware of the programmes it implemented. The sadness is that those teams may now well disperse. I welcome what you are doing with schools. Would you agree with me that you need also to work with local colleges, in the way that the ODA did, and what you need to do is, in a sense, take the baton and do...
  • Question and Answer Session: Olympic Park Legacy Company (Supplementary) [4]

    • Question by: Mike Tuffrey
    • Meeting date: 16 March 2011
    Can I touch on the sustainability assurance aspects. The Commission for a Sustainable 2012 does not just do the construction and the staging of the Games, it includes legacy, albeit that process is going to come to an end in about 2013. The first question, for the record, is do you welcome that scrutiny and will you cooperate fully with the Commission for a Sustainable 2012 for the legacy aspects?
  • Question and Answer Session: Olympic Park Legacy Company (Supplementary) [5]

    • Question by: Gareth Bacon MP
    • Meeting date: 16 March 2011
    I am interested in the cost of running the sports venues once they are into legacy mode. I understand that the OPLC will be responsible for the Stadium, the Aquatics Centre, the mixed sports venue and the tower. Do you expect the sports venues will require public subsidy once they are in legacy mode to keep them afloat, or will they stand on their own two feet?
  • Question and Answer Session: Olympic Park Legacy Company (Supplementary) [6]

    • Question by: Mike Tuffrey
    • Meeting date: 16 March 2011
    I wanted to look at the housing side of what you are doing and dig into the finances behind that will underpin the proportions between social affordable, owner occupied and, indeed, private rented possibly. When you were here last time we talked a lot about the remediation and the 60 centimetres and the impact of switching to the housing that you gave us the pictures for where there is a garden at the back. Can you update us on your financial modelling about the additional costs that are associated with remediation for family sized housing and how that impacts the...
  • Question and Answer Session: Olympic Park Legacy Company (Supplementary) [7]

    • Question by: Murad Qureshi
    • Meeting date: 16 March 2011
    Can I come to the sports legacy which has been touched on briefly by Gareth on the public subsidies. I am concerned that we do not have the Wimbledon effect which is we only play tennis for a few weeks after the Games and that is it. The role you play in that: firstly, what are you doing to help the Mayor achieve his 90% community use target for the Olympic Park in legacy?
  • Question and Answer Session: Olympic Park Legacy Company (Supplementary) [8]

    • Question by: Roger Evans
    • Meeting date: 16 March 2011
    Can we return to the subject of converting the venues please. Baroness Ford you said to the Select Committee a year ago that an additional £450 million might be required for conversion after the Games and you were going to go through this estimate line by line to work out exactly how much would be required. Have you reached a conclusion on that exercise?
  • Question and Answer Session: Olympic Park Legacy Company (Supplementary) [9]

    • Question by: Nicky Gavron
    • Meeting date: 16 March 2011
    I have very little time so I am going to ask for a very brief answer. How many of the social rented homes - or homes originally planned to be social rented - available between 2012 and 2016 do you think the new affordable rent model will apply to?
  • Question and Answer Session: Olympic Park Legacy Company (Supplementary) [10]

    • Question by: Tony Arbour
    • Meeting date: 16 March 2011
    I would like to know when and how much you expect to generate from the capital receipts for the five neighbourhoods on the Olympic Park? It is of extreme importance to the boroughs that we should get some sort of handle on this because this is the only way that Londoners who contributed to the cost of the Olympics are likely to get a dividend. Have we got a bottom figure? I have listened to you several times say that really you are not trying to evade financial questions and you are working very hard on it but you must...
  • Question and Answer Session: Olympic Park Legacy Company (Supplementary) [11]

    • Question by: John Biggs
    • Meeting date: 16 March 2011
    ): Thank you, Chair. Jennette Arnold AM and I are the two Constituency Members for the area that you are operating in. I am a bit worried by my question because it covers an area which you have not said anything about. Jennette and I represent the people of that area. You have done a lot of good work on physical infrastructure, stadiums, facilities and park planning but you have said nothing about the communities and how what you are doing is there to address the needs and the potential economic prosperity of those communities. Can you tell us what...
  • Question and Answer Session: Olympic Park Legacy Company (Supplementary) [12]

    • Question by: Andrew Boff
    • Meeting date: 16 March 2011
    Could you tell me please how long Londoners will have to wait before they can start to use the venues and visitor attractions on the Olympic site?