  • Potential for Further Budget Increases (Supplementary) [1]

    • Question by: Damian Hockney
    • Meeting date: 25 April 2007
    Sir Roy, how much of the £500 million construction contingency has so far been earmarked to be spent? There has been a lot of talk about this and a lot of rumours in the industry.
  • Potential for Further Budget Increases (Supplementary) [2]

    • Question by: Damian Hockney
    • Meeting date: 25 April 2007
    My only point really on this is that it is in that area where costs can so easily run away. In the industry, there are rumours; you speak to any of the major contractors or the journalists in the area, and they will tell you that £350 million of the £500 million has so far been earmarked, and that insiders within the ODA have told them this.
  • Potential for Further Budget Increases (Supplementary) [4]

    • Question by: Damian Hockney
    • Meeting date: 25 April 2007
    So it will not go to CLM (CH2M Hill International, Laing O'Rourke, Mace)? They will not be the people who will do it?
  • Potential for Further Budget Increases (Supplementary) [6]

    • Question by: Damian Hockney
    • Meeting date: 25 April 2007
    The fact that so few people appear to have tendered for the Aquatic Centre does that not concern you in terms of possibilities?
  • Potential for Further Budget Increases (Supplementary) [14]

    • Question by: Damian Hockney
    • Meeting date: 25 April 2007
    So if that £500 million contingency can last up to the end of next year, then how much more of the overall contingency budget that the Government has aside, which has been the cause of so much controversy, do you think you will need?
  • Legacy (Supplementary) [7]

    • Question by: Jennette Arnold OBE
    • Meeting date: 25 April 2007
    It is just a quick one. I understand that the delay at Hog Hill has been caused by you finding a particular wildlife there that needs to be preserved, and there has been six months delay to date. Can you guarantee us that it will not be a year's delay or 18 months' delay? Where are we with that?
  • Legacy (Supplementary) [16]

    • Question by: Jennette Arnold OBE
    • Meeting date: 25 April 2007
    So it has been sorted now and it will be finished by September? That is what you are saying?
  • Legacy (Supplementary) [18]

    • Question by: Jennette Arnold OBE
    • Meeting date: 25 April 2007
    So the newts will be rehoused?
  • Infrastrucutre and Regeneration (Supplementary) [3]

    • Question by: Jennette Arnold OBE
    • Meeting date: 25 April 2007
    I want to go back to jobs and I want to talk about the jobs that are your responsibility. Can you confirm for us the total amount of jobs projected? I was present at a recent presentation by your excellent Head of HR which really electrified the room, local communities, and put meat around the skeleton of the plans. I would like you to confirm with us here today the absolute numbers that you are expecting to employ. I also understand that you have employed - is it your first 500 or 5,000 people? I saw something printed this week...
  • Potential for Further Budget Increases

    • Reference: 2007/0026-1
    • Question by: Damian Hockney
    • Meeting date: 25 April 2007
    Can you guarantee that there will be no further increase in the ODA budget announced by Tessa Jowell in March?