  • Lead off question - Delays to Crossrail (Supplementary) [1]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you. Mr Mayor, just ten weeks ago, in answer to a Mayoral question (MQ), you stated, “The Elizabeth line remains on course to open as planned in December 2018”. The Commissioner, in the TfL Board report of 25 July [2018] stated, “Crossrail remains on course to open as planned in December”. Sir Terry, on 6 June, when the Transport Committee visited Tottenham Court Road with you, you gave me an absolute assurance that the opening of Crossrail would be in December. You even confirmed the date, Sunday, 9 December when the Queen would be opening...
  • Lead off question - Delays to Crossrail (Supplementary) [6]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Thank you. To come back to Crossrail, on this side [of the table] we definitely recognise the scale of this project but once completed it will be a big success for London. I am definitely looking forward to when it opens. You may be aware of Rob Holden’s [CBE, Chairman, High Speed 1] letter last week in The Times where he stated, “The problems with Crossrail arose from the decision taken in 2011 to delay the procurement of new rolling stock, a decision that has affected the commissioning of those new trains ... signalling was always going...
  • Lead off question - Delays to Crossrail (Supplementary) [9]

    • Question by: Caroline Russell
    • Meeting date: 06 September 2018
    Caroline Russell AM: Thank you, Chairman. I want to ask about the experience of the passengers who are waiting to use this line but before I get on to those questions I want to pick up on something that Sir Terry said at the very beginning. You said, “We mitigated one risk and others materialised”. I wonder if you could expand on that a bit more, whether that is what has caused this decision about the delay.
  • Lead off question - Delays to Crossrail (Supplementary) [14]

    • Question by: Keith Prince
    • Meeting date: 06 September 2018
    Keith Prince AM: Thank you, Chairman. Good morning, Sir Terry. I am trying to get some dates straight in my head. You mentioned a Board meeting in July [2018] where it was raised that there could be problems. Could you tell me the date of that meeting in July, please?
  • Transport Strategy (Supplementary) [7]

    • Question by: Len Duvall OBE
    • Meeting date: 28 June 2017
    Len Duvall AM: Thank you very much. To go back to the most challenging issue and just briefly about what, Mike, you said around technology and when technology becomes available, we know that that is constantly evolving and speeding up in some cases. Val, in answer to the question from Assembly Member Bailey, you talked about how this document really is what is in the business plan we are concentrating on and you have no long‑term plans, but in the direction of travel of the document it is quite clear you are supporting the Assembly Transport Committee’s plans for road...
  • LFEPA Cuts and the Safety of Londoners

    • Reference: 2015/3980
    • Question by: Fiona Twycross
    • Meeting date: 02 December 2015
    Since 2009/10, the London Fire and Emergency Planning Authority has had to make cuts of £105.8 million and a further £50 million has been taken from the LFEPA reserves. Are you confident that in light of these and future budget cuts, the London Fire Brigade will continue to be fit for purpose and can ensure the safety of Londoners?
  • Dissolution of LFEPA

    • Reference: 2015/3981
    • Question by: Tony Arbour
    • Meeting date: 02 December 2015
    In light of the similar responses from the Mayor, Assembly and Fire Authority to the Government's consultation 'Enabling closer working between the Emergency Services', what impact do you envisage the dissolution of LFEPA and the establishment of a Deputy Mayor for Fire and Emergency Planning would have on the London Fire Brigade?
  • Impact of climate change on your work

    • Reference: 2015/3982
    • Question by: Jenny Jones
    • Meeting date: 02 December 2015
    Are you well prepared for the impact that a changing climate might have on the fire brigade's work over the coming decade?
  • Closure of Westminster Fire Station

    • Reference: 2015/3984
    • Question by: Murad Qureshi
    • Meeting date: 02 December 2015
    How has the closure of Westminster fire station impacted attendance times in the City of Westminster?
  • Closure of Knightsbridge Fire Station (1)

    • Reference: 2015/3985
    • Question by: Murad Qureshi
    • Meeting date: 02 December 2015
    How has the closure of Knightsbridge fire station impacted attendance times in the City of Westminster?