Asked of 2

  • Lead off question - Delays to Crossrail (Supplementary) [1]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you. Mr Mayor, just ten weeks ago, in answer to a Mayoral question (MQ), you stated, “The Elizabeth line remains on course to open as planned in December 2018”. The Commissioner, in the TfL Board report of 25 July [2018] stated, “Crossrail remains on course to open as planned in December”. Sir Terry, on 6 June, when the Transport Committee visited Tottenham Court Road with you, you gave me an absolute assurance that the opening of Crossrail would be in December. You even confirmed the date, Sunday, 9 December when the Queen would be opening...
  • Lead off question - Delays to Crossrail (Supplementary) [6]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Thank you. To come back to Crossrail, on this side [of the table] we definitely recognise the scale of this project but once completed it will be a big success for London. I am definitely looking forward to when it opens. You may be aware of Rob Holden’s [CBE, Chairman, High Speed 1] letter last week in The Times where he stated, “The problems with Crossrail arose from the decision taken in 2011 to delay the procurement of new rolling stock, a decision that has affected the commissioning of those new trains ... signalling was always going...
  • Lead off question - Delays to Crossrail (Supplementary) [9]

    • Question by: Caroline Russell
    • Meeting date: 06 September 2018
    Caroline Russell AM: Thank you, Chairman. I want to ask about the experience of the passengers who are waiting to use this line but before I get on to those questions I want to pick up on something that Sir Terry said at the very beginning. You said, “We mitigated one risk and others materialised”. I wonder if you could expand on that a bit more, whether that is what has caused this decision about the delay.
  • Lead off question - Delays to Crossrail (Supplementary) [14]

    • Question by: Keith Prince
    • Meeting date: 06 September 2018
    Keith Prince AM: Thank you, Chairman. Good morning, Sir Terry. I am trying to get some dates straight in my head. You mentioned a Board meeting in July [2018] where it was raised that there could be problems. Could you tell me the date of that meeting in July, please?
  • Use of Statistics (Supplementary) [10]

    • Question by: Damian Hockney
    • Meeting date: 08 November 2006
    The problem is when the Chair of the Federation is saying what he says, which is so seriously strong when he says that it is being reported it is far below what really happens, underplayed for political reasons, you can play with statistics in that sense and the public does not feel that we have gotten on top of it. I think that independent statistics surely are the answer.
  • Transport Safer Neighbourhood Teams (2) (Supplementary) [7]

    • Question by: Graham Tope
    • Meeting date: 08 November 2006
    I take the point, wholly, that the train operating companies should be paying for their policing. Historically they do not. I do not think the public is going to be much impressed by this turf war.
  • Use of Statistics (Supplementary) [6]

    • Question by: Angie Bray
    • Meeting date: 08 November 2006
    It was suggested to me that this had been requested by TfL in order to collect figures on the congestion charge and people's journey times and choices.
  • Costs of Policing Heathrow (Supplementary) [3]

    • Question by: John Biggs
    • Meeting date: 08 November 2006
    Thank you for that answer. I freely admit this is a semi-planted question. The question is not planted but I received a briefing from the police several months ago precisely as part of the strategy which I think the Authority supports of seeking to reclaim funding for policing at London City Airport, and I quite strongly support that, it is a very profitable enterprise. As I understand it the figures are that currently policing at Heathrow costs roughly £48 million a year, of which we recover £26 million, and we want to increase that to £35 million. From the public...
  • Costs of Policing Heathrow (Supplementary) [4]

    • Question by: John Biggs
    • Meeting date: 08 November 2006
    London City Airport; roughly we spend £7 million on policing - I think this is public information - and we are hoping to recover £5 million of that £7 million from them. That is not unreasonable.
  • Complexity of Police Panels and Committees (Supplementary) [2]

    • Question by: Valerie Shawcross
    • Meeting date: 08 November 2006
    Thank you, Chair. I think you have put your finger on it when you say partly a problem of transition. My experience has been that the public and the elected representatives of the public are not yet quite clear how the new system should be working, and there is perhaps some hanging on to old consultative contact structures that could really be burned back in order to save police time, because there is some concern about use of police time in the evenings if everybody was clear about how they could access the new consultative and dialogue framework. I would...