  • Lead off question - Delays to Crossrail (Supplementary) [1]

    • Question by: Caroline Pidgeon
    • Meeting date: 06 September 2018
    Caroline Pidgeon MBE AM: Thank you. Mr Mayor, just ten weeks ago, in answer to a Mayoral question (MQ), you stated, “The Elizabeth line remains on course to open as planned in December 2018”. The Commissioner, in the TfL Board report of 25 July [2018] stated, “Crossrail remains on course to open as planned in December”. Sir Terry, on 6 June, when the Transport Committee visited Tottenham Court Road with you, you gave me an absolute assurance that the opening of Crossrail would be in December. You even confirmed the date, Sunday, 9 December when the Queen would be opening...
  • Lead off question - Delays to Crossrail (Supplementary) [6]

    • Question by: Florence Eshalomi MP
    • Meeting date: 06 September 2018
    Florence Eshalomi AM: Thank you. To come back to Crossrail, on this side [of the table] we definitely recognise the scale of this project but once completed it will be a big success for London. I am definitely looking forward to when it opens. You may be aware of Rob Holden’s [CBE, Chairman, High Speed 1] letter last week in The Times where he stated, “The problems with Crossrail arose from the decision taken in 2011 to delay the procurement of new rolling stock, a decision that has affected the commissioning of those new trains ... signalling was always going...
  • Lead off question - Delays to Crossrail (Supplementary) [9]

    • Question by: Caroline Russell
    • Meeting date: 06 September 2018
    Caroline Russell AM: Thank you, Chairman. I want to ask about the experience of the passengers who are waiting to use this line but before I get on to those questions I want to pick up on something that Sir Terry said at the very beginning. You said, “We mitigated one risk and others materialised”. I wonder if you could expand on that a bit more, whether that is what has caused this decision about the delay.
  • Lead off question - Delays to Crossrail (Supplementary) [14]

    • Question by: Keith Prince
    • Meeting date: 06 September 2018
    Keith Prince AM: Thank you, Chairman. Good morning, Sir Terry. I am trying to get some dates straight in my head. You mentioned a Board meeting in July [2018] where it was raised that there could be problems. Could you tell me the date of that meeting in July, please?
  • Transport Strategy (Supplementary) [7]

    • Question by: Len Duvall OBE
    • Meeting date: 28 June 2017
    Len Duvall AM: Thank you very much. To go back to the most challenging issue and just briefly about what, Mike, you said around technology and when technology becomes available, we know that that is constantly evolving and speeding up in some cases. Val, in answer to the question from Assembly Member Bailey, you talked about how this document really is what is in the business plan we are concentrating on and you have no long‑term plans, but in the direction of travel of the document it is quite clear you are supporting the Assembly Transport Committee’s plans for road...
  • Safer Neighbourhood Teams (Supplementary) [4]

    • Question by: Brian Coleman
    • Meeting date: 13 December 2006
    Is this a point of order?
  • Catastrophic Incident Preparations (Supplementary) [1]

    • Question by: Jennette Arnold OBE
    • Meeting date: 08 December 2004
    I wonder if you might just draw down a little bit and say is your planning based on a sector response. Listening to you, yes, you have all this equipment, but we are just used to seeing fire engines moving from A to B. How would you respond to a sector? Are you saying that you have enough equipment and resources within a given sector, and so that that would, in itself, support a catastrophic incident in that sector?
  • Catastrophic Incident Preparations (Supplementary) [2]

    • Question by: Jennette Arnold OBE
    • Meeting date: 08 December 2004
    A lot of your learning came about after 9/11. Have you been around the table with your New York colleagues recently? I am just trying to get a sense of whether the equipment we have bought since 9/11 is really state-of-the-art. Is that something for the next two years, or should we be finding ways of working with people from Spain, New York, more so, because clearly, things move on in other worlds?
  • Catastrophic Incident Preparations (Supplementary) [3]

    • Question by: Jennette Arnold OBE
    • Meeting date: 08 December 2004
    Last night in my constituency there was a major meeting because of concerns of movement of ordinary engines. What can you say to Londoners today in terms of your readiness from your service and working in collaboration with colleagues. Are you ready?
  • Orisis Exercise (Supplementary) [1]

    • Question by: Jennette Arnold OBE
    • Meeting date: 08 December 2004
    Surely you have learnt from that exercise and tested, and what did you use at that exercise, because you are saying ' in answer to question 363/2004 ' you are waiting for more equipment. What is happening now?