  • Question and Answer Session: COVID-19 Recovery - The Next Steps for London (Supplementary) [12]

    • Question by: Joanne McCartney
    • Meeting date: 04 March 2021
    Joanne McCartney AM: My first question is to Danny Thorpe, if I can. It is a general question. The pandemic has meant that many people have lost or are likely to lose their jobs in the forthcoming months. What retraining opportunities are you supporting for those people who are in that position?
  • Vision for Old Oak Common (Supplementary) [2]

    • Question by: Joanne McCartney
    • Meeting date: 07 September 2017
    Joanne McCartney AM: Thank you. I want to ask about the National Audit Office (NAO) report last year. It was reported in that report that the DfT had asked HS2 to assess the impact of extending the timetable for phase one up to 12 months. I am just wondering what impact that would have on your development schedule?